We have implemented the Time Sheet feature of PWA to track actual time spent on projects. We would like to decouple actual time entered from changing either timelines or percentage complete. Is there anyway to configure Time Sheets to just capture actual time spent and not automatically modify the project plan in anyway? Put simply time sheets are a method of capturing time spent for reporting purposes and not to reflect project progress.
Thanks
May 04 2022 02:46 PM
May 04 2022 03:27 PM
Hello @NSocci ,
Do you have the "Single Entry Mode" option set on the "Timesheet Settings and Defaults" page? If so, Uncheck that, that way the updates from the Timesheet do not create Task Status updates.
Paul
May 05 2022 06:43 AM
May 09 2022 05:27 AM
No worries @Dale_HowardMVP
@NSocci Did removing the Single Entry Mode option give you what you needed?
May 09 2022 06:13 AM
@Paul Mather Thanks for checking in. We are still exploring both options. I'll let you know the outcome.