Forum Widgets
Latest Discussions
Can't reduce row height - tried everything!
Hi there, I have a master plan which brings together a number of subprojects. I want to display just the summary tasks of each subproject to show the phasing of our entire portfolio. Even though row height under the gridlines menu is set to 1, wrapped text is off, and there are no labels on the gantt above/below the bar (only inside), I can't seem to get rid of the white space between rows. All ideas welcome! Thanks, NaomiNaomiBrillSep 23, 2025Copper Contributor116Views0likes10CommentsView all upcoming tasks for all projects in Project Server
How do you create a view in Project Server that shows all upcoming tasks (for example, from today to the end of next month) and their start/finish dates for all projects that are in Project Server? This way a Server user can see all upcoming tasks for the Enterprise, without having to go into each individual schedule? If it's not possible to create such a view, what are best practices for extracting this data into an excel Pivot Table?BrettPhifer_SCISep 18, 2025Copper Contributor26Views0likes0CommentsWhat MS Project Online Retiring Means
Hey all - there is probably a decent amount of confusion as to what the recent announcement from Microsoft regarding Project Online means and who it affects, so I made a video to explain. You can check it out here: https://youtu.be/x9efcEEHt_EKennyArnold_SSISep 11, 2025Brass Contributor102Views0likes1CommentBaseline fallback formula fails in project center
Hi Community, I have multiple projects: some have only a single baseline, some have two (Baseline and Baseline 1), and others have none. Later, I created a new project‑level, date‑type custom field. In this new field, I used the following formula: IIf([Baseline 1 Start] = ProjDateValue("NA"), [Baseline 1 Start], [Baseline Start]) The issue is: When I add this custom field to the Project Center view, the column shows as empty. When I open the same project in Project Professional (desktop) and check the Project Information, the field displays #ERROR. Has anyone run into this before or know the correct approach for checking if Baseline 1 exists, and otherwise falling back to the main Baseline date? Any suggestions or ideas would be greatly appreciated. Thanks in advance! Allow me to tag: Dale_HowardMVP John-projectKnowledgeseekerSep 03, 2025Brass Contributor236Views0likes10CommentsAlert - external linkn
Hi all, I'm using Windows 11 version 24H2, and whenever I launch Microsoft Project Pro 2019 (with an auto-macro enabled), I get the following warning, in english it sounds like: "This project contains links to one or more data sources that may be unsafe and have been disabled. Do you want to enable these data sources? Only do this if you trust the source of the file." I've already checked the Trust Center settings, enabled all macros, and reviewed everything under Options > Trust Center > Trust Center Settings, but nothing changes. It appears before running vba code, so displayalert = false (or similar) does not work. I also removed all VBA code and deleted every task to make sure no external links were hiding anywhere — but the warning still appears every time. There are no obvious external links (in tasks or in code), so I'm a bit stuck. Any idea where else I should look or how to get rid of this alert? Thanks in advancinquisitoreAug 21, 2025Copper Contributor146Views0likes6CommentsOpening project plan error
Kindly assist, When trying to open my project plan, the following error '1004' Please assist with what happenedJeanineB007Aug 18, 2025Copper Contributor70Views0likes2CommentsAssignments - inconsistency oData-feed and PWA-GUI?
Dear all, we tried to identify all user resources in our Project Online environment that don't have an assignment, hence not are assigned to any task in any project. Idea was to use the Project Online oData feed ".../_api/projectdata", query the table "Assignments" for resources included and join with table "Resources" on ResourceId to get all resources that are not referenced in the table "Assignments". The result was looking reasonable. However, cross-checking some of the resources that shouldn't have assignments with the data in PWA-GUI, via page Resources (select resource and display assignments) showed that for some of those, individual assignments are shown in the PWA-GUI. Could you help me to get my head around this? Did we look in the right place to find resources without assignments? In theory and my understanding, the table "Assignments" should be consistent with what is shown in the PWA-GUI. We already checked for publish status of the relevant project, the assignment observed had been published 3 days ago. Kind regards, PetterCuriousProjectUserAug 18, 2025Brass Contributor62Views0likes1CommentCreating a Project through Graph API "msdyn_CreateProjectV1"
I want to create a new Project online plan using Microsoft Graph API, so i used this end point and action inside my flow:- now the action will run successfully, and it should have created a new Project with subject = "Subject Test from automate", as follow:- but i can not find the new project inside the UI:- any advice?johnjohn-PeterAug 18, 2025Iron Contributor68Views0likes1CommentPFTW: Make or Promote Subtask Grayed Out Sporadically
I have two separate projects that were created in PFTW. One of them I can still make and promote subtasks (not grayed out) and the other project I was able to make and promote subtasks but now both options are grayed out. I have tried to do this from Project Accelerator, PFTW, and Planner and cannot do it from any of the apps. This is the image from the Planner access for the WBS without the functionality accessible: Here's a screenshot from the WBS where I can access: I am not the only one with this issue and we seem to have the correct licensing as we can access the functionality in some projects but have lost it in others. Any assistance troubleshooting and resolving this is greatly appreciSolvedDXProgramMgrAug 08, 2025Copper Contributor374Views0likes4Comments
Resources
Tags
- Project691 Topics
- Online287 Topics
- Project Desktop153 Topics
- Project Server151 Topics
- office 36597 Topics
- developer76 Topics
- 201664 Topics
- On Premise54 Topics
- api51 Topics
- Reporting41 Topics