Forum Widgets
Latest Discussions
MS Teams shift and MS Project online integrations
Hi, we are considering using MS Teams shift app to schedule our team. We also use MS Project online to track our team tasks. Is there any integration available that shows our team members task that have been assigned iin MS Projects, when looking at their shift in MS team shift app? At the moment, I am manually adding an assigned task in the 'shift notes' field in MS Teams shift - ideally I'd like to populate this field automatically from MS project online assigned tasks. thanksMatt_ThomsonDec 05, 2025Copper Contributor1KViews0likes2CommentsPlanner and Projects 3 online - getting this onto desktop app
Hi, We have been using Planner and Projects 3 online for the last few months and we needed a bit more functionality, so we downloaded the Project Professional desktop app as per the instructions. Now I want to get all my plans/projects that is in my planner and Projects 3 online accessible or available in Project Professional on my desktop and I have no idea how to do this; please can you assist. I cannot find a way to download paths or files from online to a local drive to be able to open them in the desktop app.MandeMDec 05, 2025Copper Contributor8Views0likes0CommentsFilter Creation
Hello, I'm hoping this community can help me. I want to create a filter that will dynamically show all in progress tasks as of today's date. I've built the filter as follows: Start is less than or equal to [Value] -AND- Finish is greater than or equal to [Value]. My issue is what to enter as the Value. Copilot said to use "Current Date," "Now()" and "Today," but none of them are dynamic. It even told me to create a new field titled "Today" using the following formula for the Custom Attribute: Today=Date(). Then, it said to reference the "Today" field as the filter Value (e.g. Start is > or = to Today). But that returns the following error: "The entry is not valid. The test value cannot be used with the field for the data you want to find or filter for." At this point I'm at a loss. This seems like it should be a very easy filter to set up; I'm surprised there isn't a built-in system filter for this already. There 's a built in filter titled "In Progress Tasks," but that only filters tasks with an Actual Start that is not blank, and an Actual Finish that is blank. Thanks in advance for any help you can provide!vincentcbvDec 04, 2025Copper Contributor96Views0likes8Comments%Complete didnt change the Finish Duration
I have an issue on my Microsoft Project work, when I update the %Complete on a single task (tracking mode) the Finish duration didnt change (the task type is Fixed Units). For example: My task was Start 20 Nov 2025 and Finish 5 Dec 2025 The actual task Start 20 Nov 2025 (on schedule) The status date is 28 Nov 2025 The %complete until the status date is 10% From the example, the task should be delayed because I cant increase the works time and the manpower but the Finish Date still locked in 5 Dec 2025. any advice or solution how to solved it? Thanks for the timestevenjDec 02, 2025Copper Contributor36Views0likes2CommentsPeople Picker in Project Detail Pages - Not Working for Already Created Projects
Hi, I have a non-mandatory field (say, "Expert") in PDP. When I create a new project, I can select the "Expert" using People Picker. When I try to open an existing project (to assign/reassign an "Expert") the People Picker feature does not work. Custom scripting is already activated. Any insight from users, as to what configuration changes should be made, would be much appreciated. ThanksBhatiaDec 01, 2025Copper Contributor119Views0likes5CommentsProject Remaining Duration as of Status Date
In a Project schedule, The % Complete entered during an update doesn't seem to push the task Finish Date as it should. The task has a Start date of 6/9/25, Finish date of 9/23/25, duration of 14.95 weeks. The Status date is 9/12/25, Actual start 6/9/25 (on schedule) but progress is 2% Complete, Remaining Duration is 13.45 wks. When I click Update Project and reschedule uncomplete work to start as of Status Date (9/12/25) the Finish Date remains 9/23/25. Shouldn't the Finish Date push to approx. 12/12/2025 based on the % complete and remaining duration? There are a handful of tasks in this schedule with a similar issue, so I would like to find out what causes this, so we can make the task Finish Dates update as you would expect when updating % complete and Remaining Duration on tasks as of the status date. If someone could point me in the right direction it would be much appreciated. There are no date constraints on the task, and "Split In-Progress tasks" is selected in the Schedule Options. We are using a 4 day a week/10 hours a day calendar. We assign Generic Resources to tasks but this particular task is NOT resource loaded. This task is linked with both a predecessor and successor, and both the predecessor and successor are statused 100% complete. Could this be why Project isn't updating the Finish Date for this task, since its successor is complete? We are using Project Server. This project has been published with the status date of 9/12/25.BrettPhifer_SCINov 28, 2025Copper Contributor174Views0likes7CommentsProject Server - Print Project Center Gantt Chart?
In on-premises Project Server, how do you print or export a view of the Gantt chart for all projects in Project Center? There is a way to print the Gantt chart view for each individual project, but we are looking for a way to print or export the Gantt Chart view which shows the summary bar for each project in Project Server (as shown in the Project Center). Is this possible with Project Server, and if so, how do we accomplish this?Brett_Phifer_SCINov 26, 2025Copper Contributor85Views0likes4CommentsStart to Finish Relationship - earliest start when connecting to two predecessors
Hi I have a scenario. Three tasks Task A - Technical documentation (preparation of it) Taks B - Project Stage Finish For Technical documetation so A have to finish before B Task B have Constraint Type - Must Finish On Task B - can change its Start/Finish date Task C - Physical Works Start - Start of works for which Technical Doc. from task A is needed so A have to finish before C Task C - will move as in reality, it will also depend upon other "tings" in project which can and will change Task A is most "submissive" task It always have to be finished before Start of B and C (sorry to all Documentation designers out there) How to create proper connection between a/m taks that always will move finish of Task A before start of B and C independent of where B and C will be moved ? I've tried to use Start to Finish, but it works only if I connect one task Below a screen shoot form my MSP I'm sorry for Polish ... but can't switch it to English (entire Office suite will .. but not MSP.. ) RZ = SF Typ Ograniczenia -> Constraint Type Jak najwcześniej -> As Soon As Possible Musi zakończyć się -> Must Finish On Rozpocznij nie wcześniej niż -> Start No Earlier Than Rozpoczęcie -> START Zakończenie -> Finish Poprzedniki -> Predecessors Następniki -> Successors Example 1 and 1A - works.... but it A is connected to only one task (A or B) Example 2 - I've connected A to B and C, but A is moved beyond B Example - same problem as above but in this scenario I've moved C before B but A... stick itself for task furthrer in future I know that I can create connection like belowe Using "Standard" connection between A and B and in the moment when situation as above will happen (A will move past B), MPS will "Scream" at me with a message that he can't finish task A but that is not a solution for me.PrzemkoNov 26, 2025Copper Contributor35Views0likes1CommentCashflow Visual report export
Hi, When I export from Visual reports using the cash flow template, my data uses Years, Quarters, and Weeks. This is fine; however, I want to edit this data. I want to show actual sequential dates, not week numbers, and I want to modify the start date of a Quarter as our business does not follow calendar quarters. There are no fields in the Pivot table selection boxes with dates, and I don't seem to be able to edit the edit section to show the date prior to export. Does anyone know how to change this? Thanks.SolvedPageAndSquireNov 21, 2025Copper Contributor76Views0likes3CommentsRecent changes could not be saved. Refresh the page to undo the changes and continue working
Hello, Over the past few days I have experienced challenges with the Project for the web part. It consists of changes not saved in the project folder. Instead, this error message appears. "Recent changes could not be saved. Refresh the page to undo the changes and continue working. Correlation ID: 6883f5fd-35f0-4bef-8423-8e5bf2dfd36f" What does this mean and what must be done so that I can use Project for the web again? Best regards,LASJOHONov 20, 2025Brass Contributor906Views0likes3Comments
Resources
Tags
- Project698 Topics
- Online290 Topics
- Project Server159 Topics
- Project Desktop156 Topics
- office 36598 Topics
- developer76 Topics
- 201664 Topics
- On Premise61 Topics
- api51 Topics
- Reporting41 Topics