Forum Widgets
Latest Discussions
Project Accelerator de Microsoft
I am running some tests with the Project Accelerator tool. I assigned a Planner Plan 1 trial license based on the documentation and previous guidance. At the beginning of February 2026 everything was working correctly, and I was able to view tasks inside the Project Accelerator application. However, as of today (February 25, 2026), the task view no longer loads, and I receive a Microsoft authentication error. It seems as if the system is now blocking access to the plan view even though the Planner Plan 1 license is still active. My question is: Have the licensing requirements changed recently?Wilbar1Feb 25, 2026Copper Contributor10Views0likes0CommentsProject Server Error when exporting to a Pivot Table using Visual Reports
Since migrating all our schedules to on-premises Project Server last year, we are getting an error message when trying to export a schedule to a pivot table using Viusal Reports. The error reads: "An error occurred and the requested action could not be completed at this time." This doesn't happen on 100% of our schedules, but the vast majority of them. What causes this error and how do we fix the issue?Brett_Phifer_SCIFeb 23, 2026Copper Contributor32Views0likes2CommentsPower Automate 'Send an HTTP request to SharePoint" only returning 300 rows of data
My PWA site has over 900 projects, but the following action only returns exactly 300 items. This feels like a returned rows limit of some sort, but I still get only 300, even when I use "&?top=1000". Any ideas?SolvedhumphrieskFeb 19, 2026Copper Contributor2.8KViews0likes9CommentsWhat MS Project Online Retiring Means
Hey all - there is probably a decent amount of confusion as to what the recent announcement from Microsoft regarding Project Online means and who it affects, so I made a video to explain. You can check it out here: https://youtu.be/x9efcEEHt_EKennyArnold_SSIFeb 05, 2026Brass Contributor426Views1like3CommentsProject Changing % Complete when entered
Why does MS Project change the % Complete value entered? We have a task with a Start date of 11/12/25 and Finish date of 1/20/27. The duration is 223.9 days based on a 4 day/10 hrs per day calendar (it is a long lead time material procurement task). The status date is 1/5/26 and the task has an Actual Start of 11/12/25. When I enter 10 in the % complete column and hit enter, Project changes this to 0%. When I enter 15 in the % complete column and hit enter, Project changes this to 5%. When I enter 50 in the % complete column and hit enter, Project changes this to 44%. I believe % Complete is either calculated or entered, but it seems if you enter a value in this field, Project shouldn't change it. What causes Project to change your % Complete value entered, and how do you get Project to display the desired % Complete for a task like this?Brett_Phifer_SCIJan 23, 2026Copper Contributor247Views0likes4CommentsIs there a way to graphically highlight all of the tasks under a summary?
Looking to create what would essentially be a coloured background for all of the tasks in the gantt chart, under a summary. Been looking online and watching tutorials, but cant find what I am looking for. The image shows what I am trying to do (was done after the fact with a PDF reader, would prefer to do it straight in MS project).mbart151Jan 19, 2026Copper Contributor92Views0likes1CommentBaseline Resourcing Assistance
Hello, I have been transferring a 1700 line schedule from a different program into MS Project. I have got the current schedule loaded and resourced, and all is working well. I have set this now as Baseline1. As part of reporting requirements, I have been asked to report current state (Baseline1) against original state (Baseline). I manually loaded the original baseline dates into Baseline Start & Baseline Finish columns on the schedule, prior to setting Baseline1 in the hope this would force those dates to become Baseline. When I run the Visual 'Baseline Work' Report for Cumulative Actual Work vs Baseline1 Work, I get the expected result, but if I also import Baseline work that data reads as 0, as it appears the resources have not applied to the baseline to create a work calculation for measurement. How can I ensure the resources are applied to all 3 fields (Baseline, Baseline1 and Actual)? Thanks in advance, KSolvedkristi_in_heelsJan 11, 2026Copper Contributor171Views0likes4CommentsFilter Creation
Hello, I'm hoping this community can help me. I want to create a filter that will dynamically show all in progress tasks as of today's date. I've built the filter as follows: Start is less than or equal to [Value] -AND- Finish is greater than or equal to [Value]. My issue is what to enter as the Value. Copilot said to use "Current Date," "Now()" and "Today," but none of them are dynamic. It even told me to create a new field titled "Today" using the following formula for the Custom Attribute: Today=Date(). Then, it said to reference the "Today" field as the filter Value (e.g. Start is > or = to Today). But that returns the following error: "The entry is not valid. The test value cannot be used with the field for the data you want to find or filter for." At this point I'm at a loss. This seems like it should be a very easy filter to set up; I'm surprised there isn't a built-in system filter for this already. There 's a built in filter titled "In Progress Tasks," but that only filters tasks with an Actual Start that is not blank, and an Actual Finish that is blank. Thanks in advance for any help you can provide!vincentcbvDec 28, 2025Copper Contributor352Views0likes13CommentsLink Procurement Tasks to deliver Just-In-Time without using up slack?
In MS Project, what is the recommended way to link procurement tasks such that the duration is the lead time of the material, the task "finishes" (material delivers) when needed by the subsequent task, and we know when to "start" the task (order material)? If we link the procurement task to the subsequent task with Finish-Start and As Late As Possible, and the subsequent task has total slack (float), this will push the subsequent task back in the schedule and use up its float. If we use Start-Finish, the dates line up but the procurement task doesn't drive the subsequent task as it should (if procurement gets behind schedule, it won't push the subsequent task). If we use the "deadline" feature, we are still tying ourselves to a date rather than letting the schedule dynamically determine when we need to order materials. What is the correct way in MS Project to schedule the ordering of materials so that delivery occurs just-in-time as determined by the scheduled start of the subsequent task?Brett_Phifer_SCIDec 27, 2025Copper Contributor196Views0likes11Comments
Tags
- Project704 Topics
- Online290 Topics
- Project Server159 Topics
- Project Desktop157 Topics
- office 365100 Topics
- developer76 Topics
- 201666 Topics
- On Premise61 Topics
- api51 Topics
- Reporting43 Topics