Hello all,
Trying to find out if there is way to show which calendar a task is using. I want a column that will show what calendar each task is assigned. I have a project that uses multiple calendars and it will make so much more sense if I can see the task calendar in a column instead of opening each one to see what is assigned.
Any help? Thank you!
Mar 04 2022 06:34 AM
SolutionHello @Tbliss ,
You can insert the "Task Calendar" column - is this what you are looking for or something else?
Paul