Mar 26 2024 04:43 AM - edited Mar 26 2024 04:46 AM
Hi everyone,
In my previous post below, I was looking for a way to show me how many of the active subtasks under a summary task were complete:
Post Location on site: Home → Project → General Discussion → MS Project (Desktop) - Total % Complete of all Total Number of Active Tasks under a Summary Task
Post Subject Line: MS Project (Desktop) - Total % Complete of all Total Number of Active Tasks under a Summary Task
Post Link:
I now am trying to achieve the following goals:
1) Determine per each active subtask, what % Complete by taking the Summary Task Baseline Cost and dividing it by the subtask Actual Cost, and then giving me a %
2) Show the % in the Baseline Cost Report in the respective month the task was actually finished
I have attached some Examples to show what I am looking for and the effects of this in MS Project Desktop and the Baseline Cost Report (Visual Report). The subtasks were baselined to start in Jan 2024 and end in Feb 2024, for the purpose of the example, I am saying we are now in April 2024:
Example 1) Example 1 showing all active subtasks complete, all Actual Costs are the same as the Baseline Cost. The Baseline Cost Report (Visual Report) shows the Baseline Cost + the Actual Cost + What % of production is complete according to the number of active subtasks complete at the time the subtask Actual Finish was inserted
Example 2) Example 2 is showing only 6/10 active subtasks complete and the Actual Cost is the same as the Baseline Cost
Example 3) Like in Example 2, only 6/10 active subtasks have been completed, but the Actual Costs for the completed subtasks vary, thus showing 94% complete at Task 6
Example 4) In this example, two additional tasks have been inserted (Delay 1 & Delay 2), these tasks are not baselined as they are not part of the plan, but they incur cost, thus driving up the Production % Complete and showing 124% after Task 6 has an Actual Finish date
Essentially, the baseline cost is used as a budget for our activities. Each month, the baseline cost value is paid into the bank account for the site, our Financial Director can then view the Baseline Cost Report (With the added field in the Monthly columns) to see where they should have been and what their actual spend is. If the site has gone over the budget, the over expenditure is taken off the next months baseline cost and the site will need to recoup the lost funds themselves.
Please note: I have tried placing the Monthly Calendar in the Rows section of the pivot table and the tasks in the Columns, however, there are too many tasks for Excel to handle this, thus the Baseline Cost Report (Visual Report) needs to shown in the format as in the Examples provided.
I would appreciate any and all advice on how to try achieve this goal. My schedules are in excess of 10 000 line items as they require a lot more detail then what is usually used.
Thanking you all in advance!
Final notes: If anyone can tell me what the specific field name is for a Summary Task (Using for formulas), it would be much appreciated. I understand there could be multiple sub summary tasks, but I have no idea if you can use a summary task/sub summary task in a formula or not?
Mar 26 2024 08:38 AM
Mar 26 2024 09:50 AM
Unfortunately, in Project it is not possible to reference values from any of the summary tasks of a subtask, within the custom field formulas.
Regards
Ignacio
Mar 26 2024 12:50 PM
Mar 26 2024 11:10 PM
Mar 27 2024 09:53 AM