Is there a way to show which calendar a task is using

Copper Contributor

Hello all,

 

Trying to find out if there is way to show which calendar a task is using. I want a column that will show what calendar each task is assigned. I have a project that uses multiple calendars and it will make so much more sense if I can see the task calendar in a column instead of opening each one to see what is assigned. 

 

Any help? Thank you!

2 Replies
best response confirmed by Tbliss (Copper Contributor)
Solution

Hello @Tbliss ,

You can insert the "Task Calendar" column - is this what you are looking for or something else?

PaulMather_0-1646404471675.png

 

Paul

Nope, that is it. I was looking under "calendar" and couldn't find anything. Didn't think to check "Task Calendar". I think this will get me what i need, Thank you!
1 best response

Accepted Solutions
best response confirmed by Tbliss (Copper Contributor)
Solution

Hello @Tbliss ,

You can insert the "Task Calendar" column - is this what you are looking for or something else?

PaulMather_0-1646404471675.png

 

Paul

View solution in original post