Timesheet app?
This site tells there is functionality for "Timesheet submission". https://www.microsoft.com/en-us/microsoft-365/project/compare-microsoft-project-management-software i´m trying to figure out if...
- Jul 18, 2020
Hello kranis ,
Yes there is an API for Timesheets: https://docs.microsoft.com/en-us/previous-versions/office/project-javascript-api/jj668309(v=office.15)
Paul
Paul_Mather
Jul 18, 2020MVP
Hello kranis ,
Microsoft used to have an official Timesheet app for Project Online but this was removed. A Project Partner called Sensei do have an app: https://www.senseiprojectsolutions.com/sensei-time-reporter-support/ or you could look to build an app with Power Apps like this example: https://powerapps.microsoft.com/en-us/partner-showcase/advisicon-inc-project-online-timesheets-mobile-app/