Import and publish approved activity updates

Occasional Visitor

Goodmorning, in Project Web app, on a project with activities assigned to resources, when these complete them on the timesheet and the project manager approves them, I cannot see the updates published on the project. Instead, by setting up an automatic approval flow, these are correctly visible. How do I import project activity updates with manual approvals?

1 Reply

Hello @D-a-v_i-d-e ,

To see the changes in PWA  / reports etc., the project needs to be published. When the approvers approves these changes, they should publish the project if they want those approvals to be included in Reports etc.

Paul