Jun 09 2023 07:01 PM
Hi All
My scenario for Working Calendar
I think that system will ask this resource in 3 week. Could you help me to fix it?
Thanks in advance
Jun 10 2023 07:01 AM
Sorry but your scenario isn't quite clear. I sounds like you have a resource that only works one day a week and when assigned to a three day task, you expect the task to expand to three weeks. Is that right? If not, please clarify what you need.
If my interpretation is correct, this is what it might look like. The resource calendar is customized so Monday is the only working day.
Then a three day task is created. To help visualize what happens the Task Usage view shows timescaled data for 3 consecutive days before the resource is assigned. Note, the Ignore Resource Calendar field is also shown to indicate the task will follow the resource's work calendar.
Now the resource is assigned at 100%. The result is that the task duration expands to cover three Monday's work.
Hope this helps.
John
Jun 11 2023 07:40 PM
Thanks for your reply, but I am sorry to made confused for you. I am refer to Project for the Web, it does not to Project desktop.
Do you have any solution on Project for the Web?
Jun 12 2023 06:18 AM
Sorry, I can't help you with Project for the Web. Hopefully one of my colleagues will jump in with an answer.
John
Jun 14 2023 04:48 PM