Forum Discussion

daibt's avatar
daibt
Brass Contributor
Jun 09, 2023

Working Calendar

Hi All My scenario for Working Calendar I create a new resource with working time 1 day per week I have make a task, assign to this resource with duration 3 days System just get 3 days in a week...

Resources