Forum Widgets
Latest Discussions
MS Project custom fields on Dataverse
I'm working on project for the web + Project accelerator (model driven). My mpp file has some custom fields such as: custom_1 , custom_2,... After importing that mpp to Project Accelerator, where /I tried to look for those custom fields on the projecttask table (Dataverse) but noresult. Do you have any solutions ? Thanks ======= Update: For better explain, I have a project on P4W, I create some custom fields (free text). Will those field be written on Dataverse's tables ? How can i get those fields to build some further solutions / features in Project Accelarator ?Solvedcuonglt0105Jan 17, 2025Copper Contributor3.2KViews0likes11CommentsMS Project master plan with many projects
Hello, I did a big master plan where i have almost 20 projects with many rows. One project has approximately 70 rows. What i need to now is to share with my coworkers a master plan which shows only 8 rows from each project, Typically only assembly and testing activity. The rest should be hidden. They are not expert to use this software, so i need to prepare for them a new master file where will be shared from actual master plan the activity what they want to see only... Does somebody know how to set it? I would definitely not go in way of using some filters. So my idea is to make a new master plan which will display only some activity from actual master plan. But how to do it? How to link it. Is there any special feature for that? Thank you to all who has some idea how to solve it.JendaJan 17, 2025Copper Contributor18Views0likes1CommentProject for web - calendar
Hi, on Project for web i've different plan with same/different resource. I've created a "calendar resource" with its own work calendar, then i'm using this resource as calendar template for all my plan. As i found here: https://learn.microsoft.com/en-us/project-for-the-web/create-and-apply-a-work-calendar Now i've this problem:resource A that need to have different calendar for each plan. So for example: resource A works on 01/15 in plan A resource A not works on 01/15 in plan B Is it possibile to achieve? How can i do that if my resource is the same? So same calendar? Can i create custom calendar for each plan but also for each resource in it? Thanks!Saaam1165Jan 16, 2025Copper Contributor19Views0likes3CommentsEnd dates of Subtask are appearing wrong
Hi there, I'm facing issue with import of xml file. When I import the file, Finish date of task having subtask, gets disturb. I am attaching the screenshot from xml file indicating the dates that I have set in it Heres the screenshot from Microsoft Project when I import the xml file After going through multiple solution, I found one of them partially working which suggested that i should turn off project calculation after each edit After applying this setting and re-loading the xml, Finish date of parent task appear corrected but for its subtasks which has duration greater than one, it still appears wrong Can someone please suggest me a solution for this ?saleemullah054Jan 16, 2025Copper Contributor265Views0likes14CommentsProject web app- No up to date data via OData feed
Hi all, we are working with the project web app. The Data stored in the project web app is pulled via the OData feed connector into a PowerBI report. The project web app is hosted on https://company.sharepoint.com/sites/pwa, the data is pulled from https://company.sharepoint.com/sites/pwa/_api/projectdata. The connection and data refresh was working for months without an issue, last week I have added two enterprise custom fields in the PWA and made some changes to the Enterprise Global. When opening the enterprise global a cache limit error appeared in Project Desktop, which was resolved by deleting the cache. I had to do a forced check in of the enterprise global in the PWA settings. I also got an error when loading the "Tasks" table in Power BI, an issue with one of the newly added enterprise custom fields was reported. This issue just appeared once, seems now to be resolved. Since then, I have not gotten any up to data from the PWA via the OData feed into PowerBI. When looking directly in the PWA the data gets updated, but gets not submitted via the OData feed anymore, some "old" versoin of the data gets submitted, I can run the data refresh against the OData feed without any issue but returns only "old" data. I also have 2 "Project Save from Project Professional" jobs under "Manage queue jobs" with job type "Cancelled" which I cannot remove / cancel from the list. How can I solve this? Thanks in advanceITManuelBIJan 16, 2025Copper Contributor86Views0likes12CommentsPlanned / actual progress
Dear Community, A more simple question where I need your comments. What is the principle difference between the (1) Progress Line and the (2) Tracking Gantt in terms of showing the planned and actual progress .. ? The Progress Line shows for a defined activity the gap between the current date (planned) and the progress (actual), while the Tracking Gantt shows the gap between the "planned activity" and the "actual activity". Many thanks SteveSteveWallJan 16, 2025Copper Contributor4Views0likes0CommentsProject for web generic resources not bookable
Hi, on Project for Web i've created some generic resources as you can see: Each of it with a hours calendar and bookable. Then i've added each resource in its own plan, for example: Pianificazione UDVC is my plan with my generic reource "Generica UDVC" The issue is that if i try to assign a task i can only find "Member of team x" instead of "Generica UDVC" , why that name instead of the name that i wrote? Also in some other plan i can't see any new bookable resource despite i can see the generic one from the "team" tab in Project admin portal. Why? Thanks!SolvedSaaam1165Jan 16, 2025Copper Contributor13Views0likes2CommentsConnecting Project central files to Planner plans
Hi there, I want to have users updating tasks in Planner plans, but have when i click the Planner link on the right i get the error below "project was unable to establish a connection with https //graph.microsoft.com" What do I need to do to connect Planner plans into a project?StuartfJan 16, 2025Brass Contributor224Views0likes4CommentsIt should be so simple…
Hello i have to show 100 projects, on one sheet, with just start date and stop date for each project. So showing start stop dates of a portfolio of projects. i have project names, work order numbers, start stop dates in my excel, for all of them! how can i show all of these projects, one per row with start stop dates out on the gantt? Do i really need to make 100 project files and sub-project off a master??! it should be so simple! Help! RJPRJPJan 13, 2025Copper Contributor133Views0likes9CommentsAssign Resources with Units = 50%
There is a resource created on "Resource Sheet" as detailed below: Resource Name: Resource 1 Type: Work Max. Units: 100% Base Calendar: Standard Just double click on this resource to get "Resource Information" dialog box and insert the values below on "Resource Availability" field: Available From Available To Units NA 02/01/2025 100% 03/01/2025 06/01/2025 50% 07/01/2025 NA 100% There is a task created on "Gantt Chart" without resource assigned as detailed below (this is the first task and there is no other custom settings): Task Name: Task 1 Task Mode: Auto Scheduled Duration: 1 day Type: Fixed Units Effort-Driven: Yes Start: Fri 03/01/25 Fisnis: Fri 03/01/25 After the assignement of "Resource 1" to this same task the "Gantt Chart" display: Task Name: Task 1 Task Mode: Auto Scheduled Duration: 1 day Work: 4 hrs Type: Fixed Units Effort-Driven: Yes Start: Fri 03/01/25 Fisnis: Fri 03/01/25 Resource Names: Resource 1[50%] The Project Start Date is Fri 03/01/25 (date format used is DD/MM/YYYY). Desired Outcome: the "Task 1" with Duration: 1 day (i.e. 8 hours) should finish on "06/01/2025" due to "Resource 1" has "Resource Availability" as detailed above (Available From: 03/01/2025 Available To: 06/01/2025 Units: 50%). If anyone knows what I might be doing wrong, I’d greatly appreciate the help.SolvedMarcos_BerenguelJan 07, 2025Copper Contributor63Views0likes3Comments
Resources
Tags
- Project668 Topics
- Online270 Topics
- Project Desktop149 Topics
- Project Server141 Topics
- office 36596 Topics
- developer71 Topics
- 201664 Topics
- On Premise52 Topics
- api47 Topics
- admin46 Topics