Forum Widgets
Latest Discussions
P4W relationships in PowerBi
Hi, I've got tables loaded from project for the web. The project tasks and project dependencies but I can't see any corresponding relationship between the two. It the project_tasks table I've tried to expand the Project_dependency_ID column but when I do this I get an error saying that there are duplicates in the project task ID although there are none. Is there a way to create a relationship between these tables?HannahM89May 22, 2025Copper Contributor4Views0likes0CommentsProject Online 'Submit' button is greyed out and the workflow is stuck at processing stage.
I created Project Online workflow using SharePoint Designer 2013 and published it. The workflow contains no errors as validated on SP Designer 2013. I create a project using the EPT that is linked to the published workflow, and updated all the mandatory fields. However the workflow submit button is greyed out even after I saved, published and checked in the project. the workflow is stuck at processing stage and it still the same even after I restarted it few times. Please advise how to make Submit button to active.ArintraMay 22, 2025Occasional Reader15Views0likes2CommentsShould the capacity of a enterprise resource change daily?
We have Project Server 2019. Should the capacity of a enterprise resource change daily in reporting database? If we have -5 month and +36 month project server additional settings, the first record in [WSS_PWA].[pjrep].[MSP_EpmResourceByDay] be resource creation date minus 5 month and the last record be current date plus 36 month. With best regards, Vasily.SolvedVasily_ZaytsevMay 20, 2025Iron Contributor458Views0likes2CommentsUnique identifier for tasks in Project on the Web
Hi, my team and I have heavily been using Microsoft Project on the web (via Teams and web). One question that does come up, how can we find unique IDs for each task? This would be highly effective for many users, as without a unique identifier, we cannot reference previously done tasks and history. Is there any plans for this? Otherwise this would severely limit our use for project on the web at this time.miteshpatel412May 14, 2025Copper Contributor1.8KViews1like13CommentsPlan 5 installed but can't see any additional features (portfolio management etc)
Hi All, I have a licence for a month of Microsoft Project Plan 5 to try it out but on both the desktop and online version I can't see any additional features compared with the Plan 3 version? Can anyone advise how to verify I am looking at Plan 5? From online videos it shows a difference view with timesheets etc down the left side. Any advice would be great as IT are just saying the licence is applied but can't see how its different? Thanks!AnnaDaisleyMay 13, 2025Copper Contributor1.7KViews0likes5CommentsProject for the Web - % complete calc error
Hi, it appears that be the order in which the effort/duration etc. fields are entered/edited, changes the calculation from % of effort completed to a % of time elapsed. When entering a new task, typically I enter those details in the order: Task name Start Finish (accept the calculated duration) Assign a resource Effort (overwriting the calculated effort - typically my resources will only work part-time on project work e.g. 4 days of effort may require 4 weeks duration) Effort completed (amend as needed) Effort remaining (accept the calculated value) % complete (accept the calculated value) ..this works fine - regardless of the start/finish (calculated duration), if I set: effort of 100 days update effort completed to 50 days effort remaining will be 50 days % complete will be 50% However, if I then change the start or finish date – at this point the % complete calc changes to an unknown calculation which is neither % of effort or elapsed time. Even when putting the fields back to their original values, % complete doesn’t return to original value?!JBatemanMay 12, 2025Copper Contributor861Views1like3CommentsPlanner portfolio not loading
Hi everyone, I usually work in Microsoft Project for the Web, but have just discovered Microsoft Planner and the ability to create portfolios ... which seems pretty smart. I have added a plan (Project for the Web) to the portfolio, but I don't get the option to add more. It's like Teams isn't loading the rest of my created plans (Project for the Web) Has anyone experienced the same problem and possibly found a solution? Best regards, LasseLASJOHOMay 12, 2025Brass Contributor112Views0likes5Comments
Resources
Tags
- Project684 Topics
- Online281 Topics
- Project Desktop153 Topics
- Project Server148 Topics
- office 36597 Topics
- developer75 Topics
- 201664 Topics
- On Premise54 Topics
- api51 Topics
- Reporting40 Topics