Forum Widgets
Latest Discussions
Project for the Web - % complete calc error
Hi, it appears that be the order in which the effort/duration etc. fields are entered/edited, changes the calculation from % of effort completed to a % of time elapsed. When entering a new task, typically I enter those details in the order: Task name Start Finish (accept the calculated duration) Assign a resource Effort (overwriting the calculated effort - typically my resources will only work part-time on project work e.g. 4 days of effort may require 4 weeks duration) Effort completed (amend as needed) Effort remaining (accept the calculated value) % complete (accept the calculated value) ..this works fine - regardless of the start/finish (calculated duration), if I set: effort of 100 days update effort completed to 50 days effort remaining will be 50 days % complete will be 50% However, if I then change the start or finish date – at this point the % complete calc changes to an unknown calculation which is neither % of effort or elapsed time. Even when putting the fields back to their original values, % complete doesn’t return to original value?!JBatemanMay 12, 2025Copper Contributor849Views1like3CommentsPlanner portfolio not loading
Hi everyone, I usually work in Microsoft Project for the Web, but have just discovered Microsoft Planner and the ability to create portfolios ... which seems pretty smart. I have added a plan (Project for the Web) to the portfolio, but I don't get the option to add more. It's like Teams isn't loading the rest of my created plans (Project for the Web) Has anyone experienced the same problem and possibly found a solution? Best regards, LasseLASJOHOMay 12, 2025Brass Contributor95Views0likes5CommentsProblems with export Microsoft Project Visual Reports to Excel
Hello, I need to export a visual report from MS Project 2013 to a pivot table in Excel. When I attempt the export, MS Project displays a message stating that I need Excel 2003 or a newer version. I have a newer version, but I am unable to complete the export. What should I do? Folow this messagemmacedoMay 08, 2025Copper Contributor297Views0likes3CommentsTeam member unable to access the Project site in project online
I have a project in project online. I assigned a task to a team member . Whenever i assigned a task , he can able to access the project. but he couldn't able to access the project site is says Access denied or request for approval. When admin or project owner opens the project site>site settings under >invitations, i can able to see who requested the site access. i don't want to manually approve. System has to assign him as a team member role to the project site & he should able to access the modules. I am using out of box permissions.Anil_kumarMay 08, 2025Brass Contributor30Views0likes1CommentAssign a resource to a task after they have finished working on a parallel task
Let's say we have two tasks: Task A (80 hrs) Task B (40 hrs) And two resources - Jane and John. Both tasks start at the same time, with Jane working on Task A and John working on Task B. With auto-scheduling and the default 5 working day week, Task A will show as 10 days and Task B will show as 5 days. Now I want to assign John to Task A once he's completed Task B, so that he can help Jane out and get the work finished faster while making optimal use of available resource. Naturally my expected outcome is that the "Duration" of Task A then becomes 7.5 days. Is there any way to achieve this? For context, here's my starting position: This seems so simple and seems like the sort of thing Project is made for, so it's sending me a little mad that I can't seem to find any resources that explain how I might tackle this.bobscompanyMay 06, 2025Copper Contributor21Views0likes1CommentTrack equipment capacity in MS Project
Hello, I have decent experience using MS Project desktop but currently struggling with how or if MS project is able to track equipment capacity in terms of quantity/units. Ideally, I would like project to alert/show capacity for an equipment based on task start/end date show capacity for future planning. For example, I have 70 samples to run on the equipment but capacity is 40 samples. I know that the 70 samples can't go through, but how can I set the equipment capacity in project to call this out? I have been tinkering with resource sheets, names, %, but don't understand how to manipulate it so that if I set an equipment capacity at 40 units (not %), it will show me capacity alerts. I also want to enter in tasks that are happening months out and would like capacity alerts to be called out in this situation too. This is how I'm tracking it in project. I don't want to put each sample as it's own line item as there are many projects with X samples so I keep it as a high level task with the project and associated sample count. Maybe it's how I am tracking that doesn't allow for tracking capacity in units? Any suggestions are appreciated. Thank you.40Views0likes1CommentDon't overrun Due Date
Hi there, I have a project and of course also a due date. How can I make sure that due date will not be overrun? If I increase the duration in row 3 ("bbb") to e.g. 9 days then the Due Date ("Ablieferung/Delivery") got overrun. When I set there in row 4 ("Ablieferung/Delivery") a predecessor, then the due date is floating into the future. General: I think this is problem is the core of every project. In the competitor software Smartsheet I can easily set up a formula that shows me the slack time. And in Smartsheet I can then set up conditional formating to show the line gets red. But how can I help myself in MS-Project?? Any help will be greatly apprecitated! Thank-you already dearly in advance! Best regards Hans ... from GermanyHans1958May 05, 2025Copper Contributor31Views0likes1CommentSave as a current project to a Project template via Teams Channel
Premium Office 365 for Workplace and Project is available under the Teams channel. I have my current project ready for future projects, and have been trying to create a template, but I could not find the option to save the existing project file structure only. Even though, I save as a copy this with a different name, the copied file works as the original file. I got the same damage on my original Project file after some cleanup in the copied file. There is no UNDO option. I have looked up this Help section about it, but it says I could find a Save As under File, but my Project file under Teams Channel does not have this function. As you see above, there is no option like I guess the Desktop version might have. Even in my Web version does not show File tab. Please advise. Thank you.SolvedujsangMay 05, 2025Copper Contributor65Views0likes3CommentsProject 2013 not talking to Excel 2019 with Visual Report Export button
In Project 2013 Standard the Visual Report Export stops when I can't find Excel - which is on my computer in 2019 Office. Can I stop it writing an error message and just continue to write the file on my HD? That way I change programmes? The error says "This operation requires that you have Excel 2003 or later installed on your computer." - but it is there!Paul-RossMay 02, 2025Copper Contributor1.2KViews0likes3Comments
Resources
Tags
- Project683 Topics
- Online280 Topics
- Project Desktop153 Topics
- Project Server148 Topics
- office 36597 Topics
- developer75 Topics
- 201664 Topics
- On Premise54 Topics
- api51 Topics
- Reporting40 Topics