Working Calendar
Hi All My scenario for Working Calendar I create a new resource with working time 1 day per week I have make a task, assign to this resource with duration 3 days System just get 3 days in a week...
John-project
Jun 12, 2023Silver Contributor
Sorry, I can't help you with Project for the Web. Hopefully one of my colleagues will jump in with an answer.
John
daibt
Jun 14, 2023Brass Contributor
I think that P4W supports 1 Working Calendar per project for all resources.