I am on a trial Project Plan 3 and I have the following question.

In project professional, I created a resource as shown here

Lakshmi11_0-1689787087580.png

1. How do I make B the default cost rate?

2. For a task on the Gantt chart, why am I not able to edit the cost rate table (I tried in project professional and pwa)? I have administrator privileges.

Lakshmi11_1-1689787499314.png

Please advise

Thanks

 

 

3 Replies
best response confirmed by Lakshmi11 (Copper Contributor)
Solution

@Lakshmi11 

You won't see the cost rate table on the Gantt Chart view because the cost rate applies to assignments. Try the Task Usage or Resource Usage views. There you can set the desired cost rate table applicable to each assignment as shown in this screen shot of the Task Usage view.

2023-07-19_10-34-45.png

Hope this helps.

John

Thanks a ton John! yes, it works.
Lakshmi11,
You're welcome and thanks for the feedback.
John
1 best response

Accepted Solutions
best response confirmed by Lakshmi11 (Copper Contributor)
Solution

@Lakshmi11 

You won't see the cost rate table on the Gantt Chart view because the cost rate applies to assignments. Try the Task Usage or Resource Usage views. There you can set the desired cost rate table applicable to each assignment as shown in this screen shot of the Task Usage view.

2023-07-19_10-34-45.png

Hope this helps.

John

View solution in original post