Forum Discussion

Lakshmi11's avatar
Lakshmi11
Copper Contributor
Jul 19, 2023

Using cost rate tab

I am on a trial Project Plan 3 and I have the following question. In project professional, I created a resource as shown here 1. How do I make B the default cost rate? 2. For a task on the G...
  • John-project's avatar
    Jul 19, 2023

    Lakshmi11 

    You won't see the cost rate table on the Gantt Chart view because the cost rate applies to assignments. Try the Task Usage or Resource Usage views. There you can set the desired cost rate table applicable to each assignment as shown in this screen shot of the Task Usage view.

    Hope this helps.

    John

Resources