Forum Discussion
Lakshmi11
Jul 19, 2023Copper Contributor
Using cost rate tab
I am on a trial Project Plan 3 and I have the following question. In project professional, I created a resource as shown here 1. How do I make B the default cost rate? 2. For a task on the G...
- Jul 19, 2023
You won't see the cost rate table on the Gantt Chart view because the cost rate applies to assignments. Try the Task Usage or Resource Usage views. There you can set the desired cost rate table applicable to each assignment as shown in this screen shot of the Task Usage view.
Hope this helps.
John
John-project
Silver Contributor
You won't see the cost rate table on the Gantt Chart view because the cost rate applies to assignments. Try the Task Usage or Resource Usage views. There you can set the desired cost rate table applicable to each assignment as shown in this screen shot of the Task Usage view.
Hope this helps.
John
Lakshmi11
Jul 19, 2023Copper Contributor
Thanks a ton John! yes, it works.
- John-projectJul 19, 2023Silver ContributorLakshmi11,
You're welcome and thanks for the feedback.
John