Sep 16 2022 03:44 AM
Hi
I am new to Ms Project and I am trying to schedule tasks in both hours and days. Eg a meeting of 3 hours ought to be less than a day.
There is no column titled hours. I will really like to have them in both hours and days - Not either or.
Thanks
Sep 16 2022 05:18 AM
Sep 16 2022 05:50 AM
Thanks for responding.
To an extent, the hours in work are not aligned to my my expectation.
It has picked certain days as 8 hours and certain one day tasks as 24hours because of the number of resources assigned to that task i guess.. so it doesnt really represent what Id like to use it for.
Eg .. We have a third party system supply workshop which three of our internal SME should attend. Three of them are represented as 8 *3 but what id really like project to show is the number of hours the workshop should last.
Sep 16 2022 06:37 AM
Sep 16 2022 08:35 AM
Thank you for explaining.
The outcome as you said it will be but it doesn't really resolve my requirement.
I would have liked the outcome on duration to be 0.50 day if I booked in a 4hour workshop (in 8hr a day working day setting)irrespective of the number of resources attending that workshop.
Sep 16 2022 08:56 AM