Scheduled hours

Occasional Contributor

Is it possible that you can assign person x for 40hours a week, and person z for 32 hours a week?

1 Reply
GKE2019 --

The only way this is possible is if the calendar for the first resource shows that the resource works 40h per week and the calendar for the second resource shows that the resource works 32h per week. Hope this helps.