Nov 27 2022 06:00 AM
How do I enter similar task information for multiple tasks simultaneously? I tried following these instructions on the MS support site, but the task information didn't get updated with the new information I entered.
I'm using Microsoft® Project® Online Desktop Client MSO (Version 2211 Build 16.0.15831.20098) 64-bit on Windows 11 (version 22H2).
Here is a recording of my steps using the Steps Recorder app in Windows:
Nov 27 2022 08:08 AM - edited Nov 27 2022 09:30 AM
I've never used the multiple task information method but I did try it on a test file and it works fine. I'm using Project 2019 Pro under Windows 10.
You show a series of screen shots with the last one supposedly showing no update, but the Priority field is not shown in the screen shot so I have to question, how do you know the update didn't "take"? For reference, the default value of the Priority field is 500 so if you "set" the tasks to that value you wouldn't know it.
John
Nov 27 2022 09:49 AM
Thanks @John-project for the quick reply.
If you compare the columns in the 1st step's snapshot with the 4th step's snapshot, you can see that the 6th column is the priority value and it is unchanged.
That's interesting that it works for you but not for me. I wonder if it has something to do with the different version I'm using.
Nov 27 2022 10:51 AM
Nov 27 2022 01:58 PM
Thanks, @John-project.
I'd like to just clarify that I'm using an "on-premises" version of MS Project (meaning it's installed on my computer and I don't have to log into a website).
Nov 28 2022 10:56 AM
Hello.
In my version 2210 in Spanish, I don't have problems, in principle, to introduce the priority in multiple tasks, and I never had it. Perhaps there is a task scheduling conflict in the project.
It must be taken into account that in the case at hand, and in which its configuration cannot be seen in its entirety, the tasks are periodic (a certain date is sought), they have an assigned task calendar, and in addition you want to apply a specific priority value. All of this, assuming that the priority serves, among other things, to redistribute (delay scheduled dates), in order to resolve resource over-allocation conflicts.
Remember that 1000 is the highest priority, and that it means freezing the task in terms of its dates, without being affected by the redistribution of resources.
Also, by default, and for some reason that I don't know yet, the priority that repeating type tasks have when they are created is 1000 instead of 500.
In short, I think that more than an error, it is about discovering:
1. The configuration of options and other data of the project in question.
2. The criteria applied by Microsoft in this complex situation.
3. What the user wants to get as a result of at least three constraints in the task.
Regards
Ignacio Martin
Nov 28 2022 11:49 AM
Nov 28 2022 12:29 PM