Jun 23 2021 08:50 AM
Hello,
A customer from me has the issue, that he cannot print with microsoft Project on the A0 format. When he wants to have it printed, he has to save it first with 'Print to PDF', and after that, send it with another tool to the printer, to print it at A0 format. He is using Microsoft Professional Project 2016
1. Is it true that Microsoft Project Cannot print on A0 with a real printer?
2. Is there a Microsoft Project version, where this is changed/solved?
Thank you in advance,
Yours sincerely,
Pieter de Visser
Jun 23 2021 09:31 AM
Jun 23 2021 09:33 AM
Jun 23 2021 09:58 AM
Jun 23 2021 10:02 AM
Jun 23 2021 10:26 AM
Jun 23 2021 10:30 AM
OK I tried this myself and it kept reverting back to 8.5x11 so I clicked on Printer Properties and then changed this setting to A0. Then it worked.
Jun 23 2021 12:22 PM
Jul 01 2021 08:09 AM
@PieterDeVisser With the Adobe PDF driver selected click the "printer properites" link just below that.