Hello Group,
How can I set up multiple resource managers for different teams/people in Project Online?
Example:
There is a resource manager for engineering staff and another resource manager for marketing staff.
If a project manager requests a specific person (engagement request) with the qualification "engineer" (I want John, the engineer) ... then the request only goes to the resource manager for engineering staff.
kind regards
Andreas
Dec 22 2022 07:28 AM
Dec 22 2022 08:47 AM - edited Dec 22 2022 08:52 AM
thank you for your input! unfortunately it doesn't work that way.
I created a lookup table:
- marketing
-- marketing staff
- engineering
-- engineering staff
and assigned people this way:
- marketing [Matthias]
-- marketing staff [Marlon]
- engineering [Andreas]
-- engineering staff [Richard]
Matthias: Resource Manager
Andreas: Resource Manager
Marlon: Team Member
Richard: Team Member
Then I changed the "My Resources" Category to:
>Resources:
Then I created a new project and
there I created a resource engagement request for both Team Members: Marlon & Richard.
Then I logged in to PWA as Andreas
And BOTH engagement requests showd up (not only the one - for Richard - from my team ... but also the request for Marlon from the other team).
And if I login to PWA as Matthias ... its the same. I see both engagement requests
Mmmhh.