Feb 13 2024 05:12 PM
I'm a new user to MS Project but have used other PMP tools. I'm trying to get initial configuration of the tool up for my new company, but have struggled with developing a portfolio analyses due to no available options in the "Analysis Primary Cost Constraint" field in the portfolio setup. I've tried to apply project costs in as many ways as I thought could be possible but still nothing. I'm using a P5 license, have tried developing custom cost fields and applying them to projects. I'm sure there is something obvious I'm missing. Any ideas would be greatly appreciated. Thank you!
Feb 14 2024 01:49 AM
SolutionFeb 14 2024 03:00 PM
@malshayeb Thank you! I was tying the custom field to the task and resource entities, not project. One final follow up question. I've applied that custom field into a few test projects to see what I get and although the custom cost field has data applied, I'm not seeing that project cost when running the portfolio analysis.
Feb 15 2024 03:03 PM
Feb 19 2024 01:22 AM
Feb 14 2024 01:49 AM
Solution