Duration not matching start / finish dates

Copper Contributor

Hello.,

I Gantt chart view i have set up a task with an estimated date of 30 days, i have selected the start date and finish dates but the Duration is showing as 197 days. 

Some tasks have more than one resource allocated

Some tasks have a Q mark after the duration where i selected estimate and others done (where i have selected estimate)

 

I think the issue somehow ties back to how the 'work' is being automatically calculated?

0 Replies