Feb 16 2024 06:27 AM
Hi,
Does anyone know what is the exact formula of the Finish date, for it to turn yellow? I know the conditon to turn red is for the date to simply be in the past, but for the date to become yellow there is no document that states exactly how and when it happens.
Any help?
Feb 16 2024 08:01 AM
Solution@Robert94 I did a little testing, and this is what I experienced.
Feb 16 2024 08:01 AM
Solution@Robert94 I did a little testing, and this is what I experienced.