SOLVED

You don't have access to it

Brass Contributor

Hi Community;

Whenever I try save editing a project on project online and I click save, right after this I get the error message 'sorry .... you don't have access to it' and it happens always with the same project.

Any suggestions?

 

Thank you in advance

4 Replies

@Knowledgeseeker We usually see that when someone else is the project owner. Have the admins check to make sure you're the owner first. 

It sounds like you've been assigned to a task in the project, which normally gives you read only access. You need to be listed as the Project Owner or granted Project Permissions with edit access.
best response confirmed by Dale Howard (MVP)
Solution
The problem was already solved, when I verified I found that I was not assigned the right access.
Thank you for your feedback.
I was not even assigned to the given project though it appeared in my list. your suggested solution is correct, actually that's what I did previosuly, adding my account to the project autorisation list.
Thank you for your feedback.

1 best response

Accepted Solutions
best response confirmed by Dale Howard (MVP)
Solution
The problem was already solved, when I verified I found that I was not assigned the right access.
Thank you for your feedback.

View solution in original post