Apr 22 2021 11:05 AM
Hello all, I have a prelim schedule going in ms project for a construction job and I am having an issue with one particular task scheduling on a Saturday. So far I have 39 tasks in the project and none of them has scheduled work on a Saturday unless done manually. The task I am struggling with is currently set up as a predecessor to a task being completed on Friday 07/30/2021 so the next available working day would be Monday 08/02/2021. The task is insisting on beginning on Saturday 07/31/2021, I cannot get to the bottom of this, I have tried deleting the task and re-doing, I have changed working time under project menu and I have weekly schedule set so no work being done on Saturdays and Sundays. I simply cannot understand why this is wasting me so much time, if anyone has any ideas or suggestion I am open to it and I can take questions and provide more information as needed. Thx.
ps. i have attached an image of the two tasks.