Resource Allocation Report

Copper Contributor

I'm using microsoft project online (not project for web).

 

I have a few projects and I need to have a report that gives me an overview of the availability in the near future.

In each project I have the enterprise resources assigned to tasks, some at 100% some less.

When I look at the reports available (I tried the capacity planning and the powebi report available at aka.ms/ProjectReports) all my resoures appear fully available for the next months.

 

I'm probably missing something very obvious.

1 Reply

Without going into too much detail, check the duration of the tasks you've assigned resources and  ensure the Finish date is correct? For example, if the task defaulted to a 1 day duration, when it should be 30 or 60 days, you will not see any future work in MSP Online or the Power BI reports.