May 06 2024 08:29 AM
Good day,
I have an issue with either my installation or my brain. I always used project this way and never had an issue before.
I have costs resources with a estimated cost allocated to a task. The task is baselined with the estimated cost. When I type in the actual cost (which is lower than the estimated amount) for the activity, the Remaining Cost drops to 0 and the estimated Cost "Cost" is changed to the actual cost I just entered.
The "Actual costs are always calculated by Project" setting is deselected. Doesn't matter if I change the setting or Task Type, the problem remains.
What am I doing wrong?
May 06 2024 08:56 AM
May 06 2024 10:49 PM - edited May 06 2024 10:53 PM
I am using 2403 (Build 17425.20176 CTR) Edit: just did an update to 2404 (Build 17531.20128 CTR), Problem still persists
Yes sorry, I mean Cost Type resource as this is a flat fee quoted and charged
No the task is not 100% complete, the contractor is claiming a portion in advanced (Yeah, I know). So if the original cost and baseline cost is $1000 and the claim is $300 with the task at let's call it 40% then surely the remaining cost should be $700?
May 06 2024 11:01 PM
May 07 2024 03:16 PM