Hello,
In Project Desktop I've assigned Cost resources to some tasks and, when tasks are marked as 100% completed, the cost resources do not appear in Actual Cost, but in Remaining Cost. Shouldn't they appear in Actual Cost?
I've found the solution of entering them as Fixed Costs in order to be taken into account in Actual Cost, but yet shouldn't they automatically appear in Actual Cost?
Thank you!
Mar 23 2023 12:22 PM
SolutionMar 23 2023 01:57 PM
@Dale Howard Thank you very much!
Yes, I've also updated the Actual Cost in the Cost table.
But I wanted to make sure that the cost resource update is not automatic and I'm not missing any facility
Thank you again!