Nov 22 2019 08:12 AM
My resources can't see their activities assigned by me on Project Web App. I checked all the permissions that they have and they are Admins.
Nov 23 2019 12:35 PM
Hello @OscarVerdin ,
Who is the Assignment Owner for these assignments? Does the Assignment Owner value match the Resource Names you are assigning to the Tasks?
Paul
Nov 25 2019 07:04 AM
Hello @Paul Mather
I'm the owner of the project, first I made the project on Project Pro before to save the project I published it on my PWA site and automatically it's saved on my PC. when I assigned resources, I selected them from the "Creat team company" and they recived the notification on their email. Yes, the Assignment Owner value match the resource names.
Thank you Paul!
- Oscar.
Nov 25 2019 09:56 AM
Hi @OscarVerdin ,
Is that screen shot for a new blank project? So when the users go to PWA Tasks {PWA site}/Tasks.aspx they see an empty grid? Any filters applied?
Nov 25 2019 10:16 AM
Hi @Paul Mather
Yes, It was a new blank project. correct, when the resources check their tasks on PWA the grid is empty, is not any filters is applicated.