Jul 20 2023 08:06 AM
Hi team
In POL, I have replaced a project schedule in Project App, by copy and pasting in a local schedule and have imported the local calendar. However, I get an error when I try to publish. Does this mean that the calendar that I’ve imported has to be in the enterprise calendar?
I’m loathed to put in many calendars into the enterprise calendar as I’ve been told it takes up a lot of resource.
Any help gratefully received
Many thanks
James
Jul 20 2023 02:03 PM
Solution