Add successor column to Project online view

Copper Contributor

Hi

I cant seem to add in the project successor column into my tasks summary view

It doesn't appear in the list of options to add so ive tried adding a custom field to pull the information from the project plan using the formula [Successors]

That creates a column but doesn't pull the info

Any ideas how I can get the column into view?

Thanks

Matt 

3 Replies

Hello @Matthew Russell ,

Only the Predecessors column is there to add by default. If you have created a new task level formula field for the Successors in the Enterprise Custom Fields admin area in PWA Settings, you will need to republish those projects for the new field to be populated with the values.

Paul

Thanks Paul
That worked. Is there any way to add successor into the online view as an editable field or is the formula field the best option?
Matt
best response confirmed by Matthew Russell (Copper Contributor)
Solution

Only the read-only calculated field option for the successor column in PWA @Matthew Russell 

1 best response

Accepted Solutions
best response confirmed by Matthew Russell (Copper Contributor)
Solution

Only the read-only calculated field option for the successor column in PWA @Matthew Russell 

View solution in original post