Nov 14 2022 05:20 AM
Hi
I cant seem to add in the project successor column into my tasks summary view
It doesn't appear in the list of options to add so ive tried adding a custom field to pull the information from the project plan using the formula [Successors]
That creates a column but doesn't pull the info
Any ideas how I can get the column into view?
Thanks
Matt
Nov 14 2022 06:50 AM
Hello @Matthew Russell ,
Only the Predecessors column is there to add by default. If you have created a new task level formula field for the Successors in the Enterprise Custom Fields admin area in PWA Settings, you will need to republish those projects for the new field to be populated with the values.
Paul
Nov 14 2022 07:09 AM
Nov 14 2022 07:54 AM
SolutionOnly the read-only calculated field option for the successor column in PWA @Matthew Russell