Oct 30 2023 01:27 PM
Hey all, just curious if any of you know why Project isn't filling up my days and leaving unused capacity?
I have customized the settings so that my standard work day is 8.5 hrs, but as you can see, my days are not being filled to this capacity, resulting in an unnecessary overallocation on the Friday...?
I have tried changing the work type between fixed work and fixed units, with and without effort driven applied, but that doesn't seem to have any impact. Also, the auto leveling doesn't seem to do anything either.
Thanks,
Joe
Oct 30 2023 04:38 PM
It sounds like you are expecting Project to optimize resources and unfortunately Project does not have that functionality.
As far as leveling, the leveling function is designed to help alleviate resources that are overallocated based on the leveling options basis setting. Leveling will NOT move resource assignments to fill in available "gaps", it will only move a resource's assignments to resolve overallocation.
Hope this helps.
John
Oct 30 2023 06:18 PM
Hi again @John-project, thanks once again for the response. I guess I sort of just figured that the asap constraint would provide that optimization, especially if the dependencies were set up? I've noticed that when playing around with very simple project/task examples, it does seem to optimize or schedule to the full daily work quota, but as I add subtasks and/or additional dependencies, it performs less well.
I would have thought that by setting the constraints to asap and setting up task dependencies, the leveling would have looked forward as well as back to start task B after task A was finished (not leaving 2 or 3 hrs in between), especially if this was all that would be needed to resolve a resource allocation...?
If that's not how it works, what are the best practices to fill these gaps? If I manually set the start time of task B to start immediately after the completion of task A, will that task still be considered as auto-scheduled? ie. If I had to insert a task somewhere before task A, would task B shift accordingly?
Oct 31 2023 11:10 AM
Oct 31 2023 12:30 PM
Thanks @John-project , that was very helpful info, you might have just saved me from going down a massive dependency rabbit hole! One question on your response, you said that some degree of manual structuring may be necessary to relieve the overallocation problem... is there any method of manual restructuring that will not break the autoschedule link? ie. will allow future modifications to flow through and adjust accordingly?
So a little context; I am trying to create a project template that can accommodate projects of varying scope. This may be a futile endeavor... I'm not sure yet.
The project type is related to sending out surveys. If the location to be surveyed is small, the project would only involve a single sample set. If the location is larger, the project would involve multiple sample sets. The tasks for each sample set are the same, but if there are multiples, they can run concurrently. For example, whether there is one sample set or 10, all of the surveys would be printed at the same time, mailed at the same time, and the waiting period for responses would be say 2 weeks, beginning and ending at the same time regardless of how many sample sets there are. The duration of the tasks would obviously increase with the number of sample sets as the volume of work increases, except for the waiting period, which is a fixed duration.
My intention was to build a template with a set of sub-tasks for each potential sample set (duplicate subprojects or sub-task groups), so I was thinking maybe the template is set up for a project of 10 sample sets, then I could add or subtract subsets to suit the scope of the project.
Each task has an estimate of the amount of work attached to it, so for example preparing the surveys might be 5 hrs per sample set, so if there were 5 sample sets to be done in the project, the total work would be 25 hrs, and this process would effectively be done as a single task in that the preparer would just start with a larger list containing all of the survey participants from each of the 5 sets. They don't need to be done sequentially, but setting up the tasks to be dependent would help with ensuring the resource allocation and duration were appropriate and maybe easier to level? Any adivce on this would be very much appreciated!
The problem is that all of the dependent tasks would basically waterfall from the preceding tasks and if I wanted to use the template for a project that only required 3 sample sets, deleting the last two would mess up all the dependencies if I don't assign them all, at least as far as I can tell so far... maybe there's a way around this that I'm not aware of? I'm still experimenting here...
I hope that kind of makes sense, here's a graphic illustrating the description of what I'm trying to do... I'm still experimenting with the best way to set this up, please don't hesitate to reach out with any advice! You can see where I've gone a little crazy trying to make sure all the dependencies are set across all the subgroups... my intention was to make sure if I deleted some, the rest would remain intact...
Thanks,
Joe
Oct 31 2023 02:26 PM
Oct 31 2023 02:59 PM
Hey @John-project , if you're referring to the screen shot, it's a program called Snagit 🙂
Thanks for the tips! I've gone down another rabbit hole... So the first task in subgroup 1 is the first task no matter what. If there is more than one sample set, then I'm thinking the first task in each subgroup is dependent on all the first tasks of the subgroups above it (ie. Create Mailout 1 -> Create Mailout 2 -> Create Mailout 3). So in the image below, the first task in each subgroup is "Create Sample Set" and I've set the predecessors to include all of the previous task rows for that task type... I think this is correct?
But the next part is where I'm kind of struggling... The next task type after the Samples have been created is to "Create the Mailout". So if there is more than 1 sample set, then is the logic that the predecessors flow with the task type? ie. Create Mailout 1 -> Create Mailout 2 -> Create Mailout 3...? or is it that Create Mailout 3 can be preceded by Create Mailout 1 and 2 AND Create Sample Set 3? Maybe this image will help clarify that question...
Thanks,
Joe
Oct 31 2023 03:38 PM
Nov 01 2023 06:29 AM
Thanks @John-project , you are correct that creating sample set 002 is not physically dependent on the creation of sample set 001 however it will pretty much always be done by the same person. Kind of like that example in the Microsoft learning about trying to have 2 people write an essay that should only take 2 hrs.... it would probably take longer and be more work to try to share these tasks between multiple resources, so i was thinking making them dependant or nonconcurrent would make sense and help with leveling. In this case would you recommend creating the dependency?
Thank you for the further explanation and I did google Heaven's to Murgatroyd, a little before my time, but I do vaguely recall that expression now, I'd forgotten all about it!
Thanks,
Joe
Nov 01 2023 08:50 AM
SolutionNov 01 2023 01:09 PM
Nov 01 2023 01:21 PM
Nov 01 2023 08:50 AM
Solution