Aug 22 2022 07:19 PM - edited Aug 22 2022 07:20 PM
I have the earned value report and table that just tells me visually or in monetary terms whether my project is ahead, on schedule or behind schedule, but I'm looking for a view, report or table that tells me quantitively in Duration how much tasks and the project overall is ahead or behind schedule.
I thought maybe the Variance table might help but the variance fields are all based on plan against baseline and my planned dates are usually the same as my baseline dates. I would think that variance based on comparing planned/baseline vs. actuals would be more accurate in whether a project is ahead or behind schedule.
I want to be able to answer the question How many days/weeks is my project ahead/on/behind schedule?
Any suggestions?
Aug 23 2022 06:04 AM
SolutionAug 23 2022 01:21 PM - edited Aug 23 2022 01:24 PM
@Dale Howard How do the Start Variance and Finish Variance use Actuals? According to MS Project the variance fields are Start-Baseline Start and Finish-Baseline finish. If actuals were used these fields should be using Actual Start and Actual Finish.
As far as how I enter my progress, when a task reached the "In Development" bucket, I set % Complete to 25%, when it gets to Ready for System Testing and System Testing I updated to 50%, Ready for UAT and UAT, 75%, and when its ready for production % completed=100
Aug 23 2022 02:35 PM
Aug 23 2022 04:10 PM
@Dale Howard Well I wonder why project was designed like that. What's the point of having Actual Start and Actual Finish fields if the Start and Finish fields always end up becoming "Actuals" fields. I do agree that updating progress using % Complete isn't the most precise technique but I find it's a good balance between accuracy and tracking effort required. I'm still able to track when a task actually starts because we also use JIRA, so I get an email alert when the developer changes the status of an item to In Development. That triggers me to set the % Complete to 25% which represents "In Development", although I get a warning sometimes because project determines not enough time has technically passed for the task to be 25% complete.
I'll try your recommendations though and see how they work.
Aug 23 2022 06:04 AM
Solution