We added 2 columns to the Summary view in Project Center, to show the Baseline Start and Baseline Finish fields. However, both columns in the Project Center are "blank" (empty) for all the projects, although the Baseline has been created for all the projects and the Baseline Start and Finish data is available and shown in each of the projects schedule.
Any assistance will be much appreciated.
Apr 30 2024 06:52 PM
May 02 2024 03:42 PM
@Dale Howard I will tell you the steps I followed to set the baseline but that is not the problem because the baseline dates are actually created/set in all the Project Schedules, However, for some reason it looks like the fields of "Baseline Start" and "Baseline Finish" dates in the Project Center dashboard are not retrieving the data from the Project Schedules.
This is the process I followed to create the baselines. I did it in Project Professional (Desktop), Click the "Project" tab, then click "Set Baseline" in the Schedule group, then click "Set Baseline" in the drop down options (the other option is "Clear Baseline" which I did not select), then click "Ok" in the next box keeping the selected options: "Set baseline" and For "Entire project".
Once the baseline was created, I saved and published the changes for each project.
Then I went to Project Online and confirmed all the projects have the Baseline dates populated in each of the Project Schedules, however the Baseline Start and Baseline Finish dates do not show in the Project Center dashboard view that I created (the columns are "blank").
Let me know if more information is needed to troubleshoot this.