Oct 31 2023 01:40 AM - edited Oct 31 2023 03:26 AM
Hi,
i have a file with some tasks that are seperated from each other and there is gap between tasks, i want to see what is actual duration of the tasks combined not the difference between start of first task and finish of the latest one as duration, is any way to do that ?
Oct 31 2023 10:50 AM
Sure, you just need a custom Duration field with a simple formula and then sum the rollup for group and summary rows.
John