project duration
Hi, i have a file with some tasks that are seperated from each other and there is gap between tasks, i want to see what is actual duration of the tasks combined not the difference between start o...
John-project
Oct 31, 2023Silver Contributor
Sure, you just need a custom Duration field with a simple formula and then sum the rollup for group and summary rows.