Jul 05 2023 12:38 AM - edited Jul 05 2023 07:17 AM
I'm working on project for the web + Project accelerator (model driven).
My mpp file has some custom fields such as: custom_1 , custom_2,...
After importing that mpp to Project Accelerator, where / I tried to look for those custom fields on the projecttask table (Dataverse) but no result.
Do you have any solutions ?
Thanks
=======
Update:
For better explain, I have a project on P4W, I create some custom fields (free text). Will those field be written on Dataverse's tables ? How can i get those fields to build some further solutions / features in Project Accelarator ?
Jul 05 2023 05:16 AM
Jul 05 2023 07:20 AM
Jul 05 2023 09:58 AM
SolutionHello @cuonglt0105 ,
Custom fields added in to the task in Project for the web are not available in the Dataverse tables.
Paul
Jul 05 2023 05:23 PM
Jul 06 2023 07:07 AM
Do you have any solutions that helps me to get information in custom field in Project for the Web and update it into Accelerator?
Jul 13 2023 03:45 AM
Please use "Copy Project" feature while creating new project. And for this, open a project having custom field and click on "Copy Project", it may take some to create new project and then check your custom field appearing in Grid view of Task tab.
Do let me know if it helps you.