Question: using 365, is there a way to link multiple project files together?

 

1 Reply
Tony --

By "365", I assume you are using the new web-based Project for the Web (Project Plan 1). If that is the case, no, there is no way to link multiple project files together? If you are using the Microsoft Project desktop application instead (Project Plan 3), yes, you can link project files together. Refer to the blog post that I wrote while I was working for Sensei at:

https://www.senseiprojectsolutions.com/insights/quickly-and-easily-create-cross-project-dependencies...

Hope this helps.