SolutionHello @Anil_kumar ,
Try {pwaUrl}/_api/ProjectData/Projects()?$select=ProjectName,_x0032_024 - the first number is encoded. If you are unsure of the properties to use in any endpoint, use the metadata endpoint the check {pwaUrl}/_api/ProjectData/$metadata
Paul