Dec 19 2023 10:52 AM
Microsoft Project Standard 2016
Custom text field
Formula:
IIf([% Complete]<> 100 And [Scheduled Finish]<Now(),"Late",IIf([% Complete]<>100 And [Scheduled Finish]-Now()<15,"Due:,""))
If % complete not equal to 100% and scheduled finish is in the past, then display "Late"
If % complete not equal to 100% and scheduled finish is less than 15 days in the future, then display "Due"
Formula works fine. However, if I open the file it does not recalculate (as the definition of Now() is likely different). Changing the duration of any incomplete tax causes recalculation properly.
Is there a way to make this recalculation occur whenever the file is opened?
Dec 19 2023 12:34 PM
SolutionDec 19 2023 12:34 PM
Dec 19 2023 12:56 PM
Thanks, I've changed it, will check tomorrow to see if it works.
Dec 19 2023 12:57 PM
Dec 28 2023 11:14 AM
Dec 19 2023 12:34 PM
Solution