Mar 18 2024 07:19 PM - edited Mar 18 2024 07:21 PM
I am using Microsoft project for the web as project management solution for my customer. I am trying to automate project operations by creating template from existing projects in project for the web as per https://learn.microsoft.com/en-us/dynamics365/project-operations/project-management/dev-copy-project...
However it is not copying values in custom columns created in project and project task entity in dataverse. I have added these columns in Copy Project Columns and Copy Project Task Columns views but still not working. Need help!
Mar 19 2024 05:19 AM
Mar 19 2024 06:46 AM
@malshayeb I have custom columns created from data verse entities Project and Project Task and not from project for the web UI. As per article in link in my original post , it says “When the action is called, Copy Project looks at the Copy Project Columns project view to determine which fields to copy when the project is copied”.
Mar 20 2024 07:41 AM