Activity Strikethrough

%3CLINGO-SUB%20id%3D%22lingo-sub-3336344%22%20slang%3D%22en-US%22%3EActivity%20Strikethrough%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3336344%22%20slang%3D%22en-US%22%3E%3CP%3EWhen%20I%20opened%20up%20my%20projects%2C%20the%20activities%20have%20strikethroughs%2C%20even%20the%20ones%20starting%20and%20ending%20past%20today's%20date.%26nbsp%3B%20I%20have%20never%20used%20the%20project%20status%20%2F%20calculate%20function%20nor%20will%20it%20let%20me%20correct%20the%20problem.%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EAny%20suggestions%3F%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EThank%20you%2C%3C%2FP%3E%3CP%3ERyann%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3336372%22%20slang%3D%22en-US%22%3ERe%3A%20Activity%20Strikethrough%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3336372%22%20slang%3D%22en-US%22%3Ercottonaro43%2C%3CBR%20%2F%3EIt%20appears%20your%20tasks%20have%20been%20inactivated.%20You%20can%20correct%20the%20issue%20in%20one%20of%20two%20ways.%3CBR%20%2F%3E1.%20Add%20the%20Active%20field%20to%20the%20view.%20It%20likely%20says%20%22no%22%3CBR%20%2F%3E2.%20Change%20the%20Active%20field%20for%20the%20first%20task%20to%20%22yes%22%3CBR%20%2F%3E3.%20Do%20a%20fill%20down%20on%20the%20Active%20field%3CBR%20%2F%3Eor%3CBR%20%2F%3E4.%20Select%20all%20tasks%3CBR%20%2F%3E5.%20Go%20to%20Task%20%26gt%3B%20Schedule%20group%20and%20toggle%20the%20Inactive%20icon%3CBR%20%2F%3E%3CBR%20%2F%3EHope%20this%20helps.%3CBR%20%2F%3EJohn%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3336632%22%20slang%3D%22en-US%22%3ERe%3A%20Activity%20Strikethrough%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3336632%22%20slang%3D%22en-US%22%3E%3CP%3E%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F917748%22%20target%3D%22_blank%22%3E%40John-project%3C%2FA%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3ESteps%204%20and%205%20worked...thank%20you!!%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3ERyann%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3337569%22%20slang%3D%22en-US%22%3ERe%3A%20Activity%20Strikethrough%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3337569%22%20slang%3D%22en-US%22%3ERyann%2C%3CBR%20%2F%3EYou're%20welcome%20and%20thanks%20for%20the%20feedback.%3CBR%20%2F%3EJohn%3C%2FLINGO-BODY%3E
New Contributor

When I opened up my projects, the activities have strikethroughs, even the ones starting and ending past today's date.  I have never used the project status / calculate function nor will it let me correct the problem.

 

Any suggestions?

 

Thank you,

Ryann

3 Replies
best response confirmed by Dale Howard (MVP)
Solution
rcottonaro43,
It appears your tasks have been inactivated. You can correct the issue in one of two ways.
1. Add the Active field to the view. It likely says "no"
2. Change the Active field for the first task to "yes"
3. Do a fill down on the Active field
or
4. Select all tasks
5. Go to Task > Schedule group and toggle the Inactive icon

Hope this helps.
John

@John-project 

 

Steps 4 and 5 worked...thank you!!

 

Ryann

Ryann,
You're welcome and thanks for the feedback.
John