Hello,
is there a Timeline (Gantt) view in Planner? Thanks
Jun 21 2022 06:15 AM
Hi,
from my knowledge you have the following options:
A - Open Schedule Tab
You will now see a calendar overview over all scheduled tasks (tasks with a due date)
B - Use one of the different group types (for example Due date)
You will now see different overviews. For example the Due date overview, which will group the task by the due date.
Kind regards
Mika
Jun 21 2022 07:17 AM
@JuaDom1991 Gantt chat is not available in Planner. You need to use the third party apps to get this view.
Jan 10 2023 01:21 AM
Easiest way is to export your plan data to Excel, format and select the columns you need (date/milestone) and then create a line chart. Takes a bit of extra time than it would in Project/Project Online/PotW but that's the simplicity of MS Planner!