Dec 12 2023 11:55 AM
I have several tasks that takes 18 to 25 days in row. Those tasks should be started from Monday to Friday. I could not made a schedule for those tasks
Dec 12 2023 01:26 PM
Here's one approach.
1. Create a "start" milestone that uses the Standard calendar (M-F) for each of the continuous tasks.
2. For those tasks that may run 24/7, set their Task Calendar to the built-in "24 hours".
3. Make the start milestone the predecessor to the continuous tasks.
Note, if most of the tasks in your plan use the Standard calendar, the start milestones will automatically take on the Standard calendar, but if your plan has a separate custom calendar (e.g. 9 hour days, etc.), then set the Task Calendar for each milestone to be the Standard calendar.
Hope this helps.
John
Dec 13 2023 02:11 AM - edited Dec 13 2023 02:19 AM
Hi
I think that using the milestone as a predecessor does not prevent its successor task from starting on Saturday or Sunday, because since the milestone has a duration of 0 days, it will not be affected by any calendar.
Perhaps dividing the continuous task from Monday to Sunday, with Jhon's idea, into Start task A (1d/Calendar Monday to Friday)) and Remaining task A (Dur-1/Calendar Monday to Sunday), linked Finish-Start.
Still, there may be exceptions where this approach may not be appropriate and would require review.
Regards.
Ignacio Martín
Dec 13 2023 08:43 AM
Dec 13 2023 09:44 AM
Dec 13 2023 12:12 PM
Dec 13 2023 12:36 PM
Dec 13 2023 12:45 PM
Dec 13 2023 02:08 PM
Dec 14 2023 08:13 AM
SolutionOr......how about this "end around run"? As soon as the "milestone" takes on a non-zero value, the Monday through Thursday only custom calendar as the Task Calendar does the trick.
John :)
Dec 14 2023 09:06 AM
Dec 14 2023 12:11 PM
Dec 14 2023 12:35 PM
Dec 14 2023 12:41 PM
Dec 14 2023 03:49 PM
Dec 14 2023 06:16 PM
Dec 15 2023 06:54 AM
Dec 15 2023 06:55 AM
Dec 15 2023 07:14 AM
Dec 15 2023 08:31 AM - edited Dec 15 2023 09:16 AM
Shahram,
You're welcome and thanks for the feedback. You might want to check out my latest reply to Ignacio for an improved approach.
John
Dec 14 2023 08:13 AM
SolutionOr......how about this "end around run"? As soon as the "milestone" takes on a non-zero value, the Monday through Thursday only custom calendar as the Task Calendar does the trick.
John :)