Jan 11 2024 05:21 AM
Hi - I'm getting a value error returned when trying to calculate dates in a formula and am looking for help.
I'm looking to calculate a series of procurement dates (shipping, manufacture etc.) which subtract duration days from previously calculated days. This depends on whether the materials are being purchased locally or internationally thus working with different holiday calendars (Tables 3&4 on another sheet).
The formula seems to work for the first column (AS) which gets the date from a VLOOKUP formula (in AV) but then returns an error in subsequent rows (AO,AK) when International is selected in column AH??
Thanks
Jan 11 2024 05:53 AM
Jan 11 2024 06:21 AM
Jan 11 2024 10:45 AM
Jan 13 2024 08:26 AM
Hi Thanks for the help - yes that clears the value error when I amend the formula to WORKDAY(AS9,AN9,Table3)... but that adds the number of days to the previous date whereas I need to subtract the dates back from the previous i.e. AO12 subtracts 5 working days from AS12 date to return the earlier date.
Weirdly when I re-entered the original formula into the cells with the minus sign the value error cleared??
Appreciate your help