Recent Discussions
Baseline Resourcing Assistance
Hello, I have been transferring a 1700 line schedule from a different program into MS Project. I have got the current schedule loaded and resourced, and all is working well. I have set this now as Baseline1. As part of reporting requirements, I have been asked to report current state (Baseline1) against original state (Baseline). I manually loaded the original baseline dates into Baseline Start & Baseline Finish columns on the schedule, prior to setting Baseline1 in the hope this would force those dates to become Baseline. When I run the Visual 'Baseline Work' Report for Cumulative Actual Work vs Baseline1 Work, I get the expected result, but if I also import Baseline work that data reads as 0, as it appears the resources have not applied to the baseline to create a work calculation for measurement. How can I ensure the resources are applied to all 3 fields (Baseline, Baseline1 and Actual)? Thanks in advance, KSolved86Views0likes4CommentsProject Changing % Complete when entered
Why does MS Project change the % Complete value entered? We have a task with a Start date of 11/12/25 and Finish date of 1/20/27. The duration is 223.9 days based on a 4 day/10 hrs per day calendar (it is a long lead time material procurement task). The status date is 1/5/26 and the task has an Actual Start of 11/12/25. When I enter 10 in the % complete column and hit enter, Project changes this to 0%. When I enter 15 in the % complete column and hit enter, Project changes this to 5%. When I enter 50 in the % complete column and hit enter, Project changes this to 44%. I believe % Complete is either calculated or entered, but it seems if you enter a value in this field, Project shouldn't change it. What causes Project to change your % Complete value entered, and how do you get Project to display the desired % Complete for a task like this?32Views0likes1CommentLink Procurement Tasks to deliver Just-In-Time without using up slack?
In MS Project, what is the recommended way to link procurement tasks such that the duration is the lead time of the material, the task "finishes" (material delivers) when needed by the subsequent task, and we know when to "start" the task (order material)? If we link the procurement task to the subsequent task with Finish-Start and As Late As Possible, and the subsequent task has total slack (float), this will push the subsequent task back in the schedule and use up its float. If we use Start-Finish, the dates line up but the procurement task doesn't drive the subsequent task as it should (if procurement gets behind schedule, it won't push the subsequent task). If we use the "deadline" feature, we are still tying ourselves to a date rather than letting the schedule dynamically determine when we need to order materials. What is the correct way in MS Project to schedule the ordering of materials so that delivery occurs just-in-time as determined by the scheduled start of the subsequent task?150Views0likes11CommentsProject Online Updates & AI Integration
Hi all, Fairly new to this discussion board but I wanted to ask if anyone is aware of any upcoming project desktop updates and potential integration of AI? From what I understand, project has never really evolved significantly and its competitors have started to take some market share. Would love to know if there is something in the works or where I could even find any information on this? It always seems to be challenging finding information. Thanks,58Views0likes1CommentVisual report don’t work
Hi I am using msproject 2016 stand alone together with office365. And I get an "unknown error" when I try to use Visual Report. anyone knows how to solve this? I have read somewhere that I need to rollback MS Project to a specific build no. I don’t know if this is the solution. If so. How do I do this and to what build version? Br Rune13Views0likes0CommentsWorkload by week/ month export to Excel
I like to use Visual report, but that doesn’t work.. I have MSProject 2016 and office 365. so I have tried to use save as (export) as xls. But I can’t get the load or week or month. anyone that can help out setup in table format. I think… the I can build the rest in Excel if needed br runeSolved146Views0likes4CommentsHow to visualize data desktop projects after PWA retirement?
This questions is a follow-up to the discussion "Data access after Project Online (PWA) retirement". From the "Data access after Project Online (PWA) retirement" discussion it is clear that data will not be moved somewhere else. We are mainly using the PWA site to enable that the data from the desktop projects can be visualized in Power BI, so that we can create project and portfolio dashboards that summarize information from both desktop projects and planner projects. Any thoughts on how this could be achieved in the future?62Views0likes1CommentProject Server Power BI Content Pack - Connect to Billed Work Hours?
Is there a way to use the templates in the Project Server Power BI Content Pack and connect to an excel spreadsheet containing the hours billed/charged to a project? Since MS Project simply calculates Actual Work based on % complete status update, we want to compare the "Actual" hours billed to a project to the Remaining Work to get a better picture of whether labor hours are on track to be over/under budgeted hours. ("Actual" hours from an export from our accounting system + "Remaining Work" from the MS Project schedule = Estimated Work at Completion; compare this to Baseline Work). Has anyone done something like this in your organization, and if so, how did you connect these 2 sets of data and create a visual for people in your organization?61Views0likes1CommentPlanner and Projects 3 online - getting this onto desktop app
Hi, We have been using Planner and Projects 3 online for the last few months and we needed a bit more functionality, so we downloaded the Project Professional desktop app as per the instructions. Now I want to get all my plans/projects that is in my planner and Projects 3 online accessible or available in Project Professional on my desktop and I have no idea how to do this; please can you assist. I cannot find a way to download paths or files from online to a local drive to be able to open them in the desktop app.89Views0likes1CommentFilter Creation
Hello, I'm hoping this community can help me. I want to create a filter that will dynamically show all in progress tasks as of today's date. I've built the filter as follows: Start is less than or equal to [Value] -AND- Finish is greater than or equal to [Value]. My issue is what to enter as the Value. Copilot said to use "Current Date," "Now()" and "Today," but none of them are dynamic. It even told me to create a new field titled "Today" using the following formula for the Custom Attribute: Today=Date(). Then, it said to reference the "Today" field as the filter Value (e.g. Start is > or = to Today). But that returns the following error: "The entry is not valid. The test value cannot be used with the field for the data you want to find or filter for." At this point I'm at a loss. This seems like it should be a very easy filter to set up; I'm surprised there isn't a built-in system filter for this already. There 's a built in filter titled "In Progress Tasks," but that only filters tasks with an Actual Start that is not blank, and an Actual Finish that is blank. Thanks in advance for any help you can provide!295Views0likes13Comments%Complete didnt change the Finish Duration
I have an issue on my Microsoft Project work, when I update the %Complete on a single task (tracking mode) the Finish duration didnt change (the task type is Fixed Units). For example: My task was Start 20 Nov 2025 and Finish 5 Dec 2025 The actual task Start 20 Nov 2025 (on schedule) The status date is 28 Nov 2025 The %complete until the status date is 10% From the example, the task should be delayed because I cant increase the works time and the manpower but the Finish Date still locked in 5 Dec 2025. any advice or solution how to solved it? Thanks for the time67Views0likes2CommentsStart to Finish Relationship - earliest start when connecting to two predecessors
Hi I have a scenario. Three tasks Task A - Technical documentation (preparation of it) Taks B - Project Stage Finish For Technical documetation so A have to finish before B Task B have Constraint Type - Must Finish On Task B - can change its Start/Finish date Task C - Physical Works Start - Start of works for which Technical Doc. from task A is needed so A have to finish before C Task C - will move as in reality, it will also depend upon other "tings" in project which can and will change Task A is most "submissive" task It always have to be finished before Start of B and C (sorry to all Documentation designers out there) How to create proper connection between a/m taks that always will move finish of Task A before start of B and C independent of where B and C will be moved ? I've tried to use Start to Finish, but it works only if I connect one task Below a screen shoot form my MSP I'm sorry for Polish ... but can't switch it to English (entire Office suite will .. but not MSP.. ) RZ = SF Typ Ograniczenia -> Constraint Type Jak najwcześniej -> As Soon As Possible Musi zakończyć się -> Must Finish On Rozpocznij nie wcześniej niż -> Start No Earlier Than Rozpoczęcie -> START Zakończenie -> Finish Poprzedniki -> Predecessors Następniki -> Successors Example 1 and 1A - works.... but it A is connected to only one task (A or B) Example 2 - I've connected A to B and C, but A is moved beyond B Example - same problem as above but in this scenario I've moved C before B but A... stick itself for task furthrer in future I know that I can create connection like belowe Using "Standard" connection between A and B and in the moment when situation as above will happen (A will move past B), MPS will "Scream" at me with a message that he can't finish task A but that is not a solution for me.73Views0likes1CommentPeople Picker in Project Detail Pages - Not Working for Already Created Projects
Hi, I have a non-mandatory field (say, "Expert") in PDP. When I create a new project, I can select the "Expert" using People Picker. When I try to open an existing project (to assign/reassign an "Expert") the People Picker feature does not work. Custom scripting is already activated. Any insight from users, as to what configuration changes should be made, would be much appreciated. Thanks162Views0likes5CommentsProject Server - Print Project Center Gantt Chart?
In on-premises Project Server, how do you print or export a view of the Gantt chart for all projects in Project Center? There is a way to print the Gantt chart view for each individual project, but we are looking for a way to print or export the Gantt Chart view which shows the summary bar for each project in Project Server (as shown in the Project Center). Is this possible with Project Server, and if so, how do we accomplish this?138Views0likes4CommentsCashflow Visual report export
Hi, When I export from Visual reports using the cash flow template, my data uses Years, Quarters, and Weeks. This is fine; however, I want to edit this data. I want to show actual sequential dates, not week numbers, and I want to modify the start date of a Quarter as our business does not follow calendar quarters. There are no fields in the Pivot table selection boxes with dates, and I don't seem to be able to edit the edit section to show the date prior to export. Does anyone know how to change this? Thanks.Solved152Views0likes4CommentsChange Print Page Order
Hello, I'm looking to see if someone can help me find how to change the order that pages are printed in Project. Personally, I know this doesn't matter because you can just line them up as you like, but my job has me make PDFs of them as well and my boss would prefer the order to be different, so if possible I'd rather find a way to make it do it the way he'd like automatically than me re-arranging the PDF pages and editing the page numbers. Essentially, they want it to show the entire date line of the gantt chart first before showing the next set of rows. I've attached 2 screenshots of the print preview, one is the order it currently is (focusing on the rows first) and the 2nd is the order my boss would like (focusing on the gantt chart dates first). Is this possible and if so, how do I go about setting it up?152Views0likes3CommentsA colored column representing holidays
I am looking for ideas as to how to create a transparent, colored visual column within an MS gantt chart representing a date range that correlates with the Christmas holidays. Basically, just a vertical bar crossing all tasks that visually indicates the holiday date range (say 12/22/25- 01/02/26) so that as you scroll through all your tasks, that bar remains constant in the gantt chart. I can do a single date bar using Status Date, but have not found a way to perform a similar function for a date range. Any ideas or tricks?Solved125Views0likes1CommentImporting csv file error
For years i am successfully using a csv file import via a certain mapping. All of a sudden this stopped working last week with multiple users. Seems there is an issue with MS Project on this. Does anyone know more or have a workaround? Thanks in advance!54Views0likes0CommentsLOE Tasks in Project Server
What is the proper way to reflect LOE (Level Of Effort) tasks in MS Project? For example, adding a task showing the PM working 10% of his time on the project, for the duration of the project. If we simply give that task a duration equal to the project, then Project cannot determine the correct Critical Path of the project. In addition, if the project duration changes, the PM will have to manually change the duration of the PM task. If we try linking this task with SS and FF relationships, the duration remains 1 day unless we input the duration, in which case we still have to update the duration as the project progresses. I have tried creating a hammock LOE task by copying and pasting links to the first and last tasks, as described in TenSix Consulting articles https://tensix.com/creating-loe-tasks-in-microsoft-project/ and https://tensix.com/more-about-level-of-effort-tasks-in-microsoft-project/ . However, this does not work in my version of Project Professional. I am only able to link either the starting date or finish date, but not both. Does anyone here have experience with scheduling this type of LOE task in MS Project? We are using on premises Project Server. We want to schedule this type of PM oversight task to plan for the estimated hours of PM time over the span of the project, have the task duration update dynamically if the project duration changes, and be able to status this PM task during the project to reflect the "actual" and "remaining" hours for the task as the project progresses.31Views0likes0Comments
Events
Recent Blogs
- Project 2016 and Project 2019 will reach end of support on October 14, 2025.Oct 14, 202412KViews4likes9Comments
- One of my favourite features in Project Online, and Project Server, has been the portfolio features that allow you do match your plan portfolio against your business drivers to ensure you are gaining...Sep 25, 20243.2KViews4likes8Comments