Recent Discussions
Change Print Page Order
Hello, I'm looking to see if someone can help me find how to change the order that pages are printed in Project. Personally, I know this doesn't matter because you can just line them up as you like, but my job has me make PDFs of them as well and my boss would prefer the order to be different, so if possible I'd rather find a way to make it do it the way he'd like automatically than me re-arranging the PDF pages and editing the page numbers. Essentially, they want it to show the entire date line of the gantt chart first before showing the next set of rows. I've attached 2 screenshots of the print preview, one is the order it currently is (focusing on the rows first) and the 2nd is the order my boss would like (focusing on the gantt chart dates first). Is this possible and if so, how do I go about setting it up?35Views0likes3CommentsImporting csv file error
For years i am successfully using a csv file import via a certain mapping. All of a sudden this stopped working last week with multiple users. Seems there is an issue with MS Project on this. Does anyone know more or have a workaround? Thanks in advance!27Views0likes0CommentsLOE Tasks in Project Server
What is the proper way to reflect LOE (Level Of Effort) tasks in MS Project? For example, adding a task showing the PM working 10% of his time on the project, for the duration of the project. If we simply give that task a duration equal to the project, then Project cannot determine the correct Critical Path of the project. In addition, if the project duration changes, the PM will have to manually change the duration of the PM task. If we try linking this task with SS and FF relationships, the duration remains 1 day unless we input the duration, in which case we still have to update the duration as the project progresses. I have tried creating a hammock LOE task by copying and pasting links to the first and last tasks, as described in TenSix Consulting articles https://tensix.com/creating-loe-tasks-in-microsoft-project/ and https://tensix.com/more-about-level-of-effort-tasks-in-microsoft-project/ . However, this does not work in my version of Project Professional. I am only able to link either the starting date or finish date, but not both. Does anyone here have experience with scheduling this type of LOE task in MS Project? We are using on premises Project Server. We want to schedule this type of PM oversight task to plan for the estimated hours of PM time over the span of the project, have the task duration update dynamically if the project duration changes, and be able to status this PM task during the project to reflect the "actual" and "remaining" hours for the task as the project progresses.9Views0likes0Commentssave forecasted data
at time 0 I create the planning, which i baseline in bsln0. at time increment 1 I update the planning with the real start/finish/ %complete (and %real work in case I want to perform SPI/CPI, ...) and I save it into baseline 1; at the same time increment 1 I make a simulation of what will be at the time increment 2. The question is: how do I save this forecast in the same file (I do NOT want to create copy of that file) without corrupting the actual data (actual start, actual finish, %complete), that I want to compare whit the real status when the time will be at the effective calendar increment 2? thanks in advance22Views0likes1CommentSchedule Opens in Read-Only Mode from Conference Room Computer
In Project Server, a Project Manager opens his schedule on a conference room computer, but it opens Read Only mode and the PM is not able to check it out and edit/publish the project. We made sure it was not already checked out, and the PM is able to open, edit and publish this schedule from his work station. As far as we can tell, this problem only occurs when opening this one schedule from the conference room computer. We have cleared the cache as described in this handy article: https://www.dalehowardmvp.com/force-check-in-stuck-projects/ but this didn’t solve the issue. I have seen another article https://www.dalehowardmvp.com/how-to-fix-corrupted-files/ about using Save for Sharing to correct possibly corrupted schedules. My question is: would doing this cause any issues since we are accessing the schedule from a conference room? We do not want to adversely affect the way the PM opens this project from their work station. Does anyone have an experience with schedules opening from the PM’s work station but opening Read-Only when accessing PWA from a conference room computer? Would Save for Sharing help in this instance? Thank you34Views0likes2CommentsTeam Assignment Visibility in Project Server
In on-premesis Project Server, I want "Engineering" Team Members with "My Task" Global permissions to be able to see all tasks that have been assigned to a generic resource that is also part of the Engineering Team Resource Assignment Pool. Then, they can self-assign or simply update the status of these tasks. The PM initially resource-loads the schedule with the generic resource, then when the project starts, we want the various teams to be able to see tasks and provide status updates, without the PM needing to manually assign resources to individual tasks in the schedules (other than the generic resource loaded when the schedule is built). What permissions in Project Server do we need to enable in order for these team members to see all tasks assigned to their teams? Using the BUild TEam page, we have added the Engineering Team Resource Assignment Pool and the individual team members to the project team, but they cannot see the project schedule or any tasks in Project Server.43Views0likes2Commentsshell.js error when loading schedule tab in PWA
Has anyone experienced this issue? In Javascript console: Uncaught ReferenceError: g_PJPrefetch is not defined in function function m() { ULSePY: ;if (g_PJPrefetch != null && g_PJPrefetch == 0) { g_PJPrefetch = 1; SP.SOD.prefetch() } } Is not displaying the shceduled data in all projects in our project Server on premises. We use sharepoint server subscription edition 201921Views0likes0CommentsWhat is a best practice for linking Just-In-Time Tasks?
In MS Project, what is a best practice for linking Just-In-Time tasks, so that a task is scheduled to take place just prior to another task, without use of date constraints or overriding scheduling logic? As an example, I have a task "task prep" that I want to complete just before "important task" starts. "Important task" has other Finish-Start predecessors that determine when it starts. The only thing driving "task prep" is that it must finish just before "important task" starts. These tasks have slack in the schedule that I want to maintain, so I can't use As Late As Possible constraint without pushing both tasks to the right and using up slack. There isn't a task preventing "task prep" from starting, so if I link "task prep" as a predecessor to "important task" with Finish-Start (FS), with As Soon As Possible, then "task prep" will be scheduled to happen long before I want to perform that task. If I use Start-Finish (SF), then the start date of "Important task" drives the finish date of "Task Prep" The dates line up, but SF dependency type is generally not recommended. Also, I do not want to use date constraints, as these are generally not recommended. How can I link these tasks so that "task prep" finishes just before "important task" while adhering to accepted scheduling standards?128Views0likes4CommentsAutomatic overwriting "Task name", after saving
Hello Community, I am asking assistance for an easy issue but so annoying: when I save a MS Project file, the row modified loses its Task Name, overwriting itself, with apprarently no reason. It is so crucial to not overwrite because I lose my work team references. Here a breakdown: I have create a MS Project file named "PROJECT MASTER PLANNER". I have imported SubProjects on the rows. I modify one or more SubProject directly on "PROJECT MASTER PLANNER". I click "Save to All" or just "Save". The SubProjects modified lose their Task Name, overwiritng automatically with "78.25_rev01". 78.25_rev01 was my first MS Project ever imported on "PROJECT MASTER PLANNER", that i do not use anymore. Below a couple of screenshot. Many thanks to whom will help me, it is blowing my mind ! AndreB. SCREENSHOT 1/2 SCREENSHOT 2/275Views0likes3CommentsProject Server Enterprise Global Freeze
We are using on-premises Project Server. The Enterprise Global Template has frozen such that once I open it, MS Project freezes and I can't get to the Organizer to remove custom views (Assuming a custom view has polluted the EGT, as the only thing we do in the EGT is create or modify custom views/tables/filters). How can I access the Organizer to "un-pollute" the Enterprise Global Template? Also, I saved our custom views in an mpp file. How can I tell which view is causing the problem with the Global Template, so I can prevent this from happening in the future? Any help would be greatly appreciated!12Views0likes0CommentsProject Remaining Duration as of Status Date
In a Project schedule, The % Complete entered during an update doesn't seem to push the task Finish Date as it should. The task has a Start date of 6/9/25, Finish date of 9/23/25, duration of 14.95 weeks. The Status date is 9/12/25, Actual start 6/9/25 (on schedule) but progress is 2% Complete, Remaining Duration is 13.45 wks. When I click Update Project and reschedule uncomplete work to start as of Status Date (9/12/25) the Finish Date remains 9/23/25. Shouldn't the Finish Date push to approx. 12/12/2025 based on the % complete and remaining duration? There are a handful of tasks in this schedule with a similar issue, so I would like to find out what causes this, so we can make the task Finish Dates update as you would expect when updating % complete and Remaining Duration on tasks as of the status date. If someone could point me in the right direction it would be much appreciated. There are no date constraints on the task, and "Split In-Progress tasks" is selected in the Schedule Options. We are using a 4 day a week/10 hours a day calendar. We assign Generic Resources to tasks but this particular task is NOT resource loaded. This task is linked with both a predecessor and successor, and both the predecessor and successor are statused 100% complete. Could this be why Project isn't updating the Finish Date for this task, since its successor is complete? We are using Project Server. This project has been published with the status date of 9/12/25.126Views0likes6CommentsCan't reduce row height - tried everything!
Hi there, I have a master plan which brings together a number of subprojects. I want to display just the summary tasks of each subproject to show the phasing of our entire portfolio. Even though row height under the gridlines menu is set to 1, wrapped text is off, and there are no labels on the gantt above/below the bar (only inside), I can't seem to get rid of the white space between rows. All ideas welcome! Thanks, Naomi203Views0likes12CommentsView all upcoming tasks for all projects in Project Server
How do you create a view in Project Server that shows all upcoming tasks (for example, from today to the end of next month) and their start/finish dates for all projects that are in Project Server? This way a Server user can see all upcoming tasks for the Enterprise, without having to go into each individual schedule? If it's not possible to create such a view, what are best practices for extracting this data into an excel Pivot Table?35Views0likes0CommentsWhat MS Project Online Retiring Means
Hey all - there is probably a decent amount of confusion as to what the recent announcement from Microsoft regarding Project Online means and who it affects, so I made a video to explain. You can check it out here: https://youtu.be/x9efcEEHt_E258Views1like2CommentsBaseline fallback formula fails in project center
Hi Community, I have multiple projects: some have only a single baseline, some have two (Baseline and Baseline 1), and others have none. Later, I created a new project‑level, date‑type custom field. In this new field, I used the following formula: IIf([Baseline 1 Start] = ProjDateValue("NA"), [Baseline 1 Start], [Baseline Start]) The issue is: When I add this custom field to the Project Center view, the column shows as empty. When I open the same project in Project Professional (desktop) and check the Project Information, the field displays #ERROR. Has anyone run into this before or know the correct approach for checking if Baseline 1 exists, and otherwise falling back to the main Baseline date? Any suggestions or ideas would be greatly appreciated. Thanks in advance! Allow me to tag: Dale_HowardMVP John-project287Views0likes10CommentsAlert - external linkn
Hi all, I'm using Windows 11 version 24H2, and whenever I launch Microsoft Project Pro 2019 (with an auto-macro enabled), I get the following warning, in english it sounds like: "This project contains links to one or more data sources that may be unsafe and have been disabled. Do you want to enable these data sources? Only do this if you trust the source of the file." I've already checked the Trust Center settings, enabled all macros, and reviewed everything under Options > Trust Center > Trust Center Settings, but nothing changes. It appears before running vba code, so displayalert = false (or similar) does not work. I also removed all VBA code and deleted every task to make sure no external links were hiding anywhere — but the warning still appears every time. There are no obvious external links (in tasks or in code), so I'm a bit stuck. Any idea where else I should look or how to get rid of this alert? Thanks in advanc210Views0likes6CommentsCreating a Project through Graph API "msdyn_CreateProjectV1"
I want to create a new Project online plan using Microsoft Graph API, so i used this end point and action inside my flow:- now the action will run successfully, and it should have created a new Project with subject = "Subject Test from automate", as follow:- but i can not find the new project inside the UI:- any advice?94Views0likes1CommentAssignments - inconsistency oData-feed and PWA-GUI?
Dear all, we tried to identify all user resources in our Project Online environment that don't have an assignment, hence not are assigned to any task in any project. Idea was to use the Project Online oData feed ".../_api/projectdata", query the table "Assignments" for resources included and join with table "Resources" on ResourceId to get all resources that are not referenced in the table "Assignments". The result was looking reasonable. However, cross-checking some of the resources that shouldn't have assignments with the data in PWA-GUI, via page Resources (select resource and display assignments) showed that for some of those, individual assignments are shown in the PWA-GUI. Could you help me to get my head around this? Did we look in the right place to find resources without assignments? In theory and my understanding, the table "Assignments" should be consistent with what is shown in the PWA-GUI. We already checked for publish status of the relevant project, the assignment observed had been published 3 days ago. Kind regards, Petter86Views0likes1CommentPDP - Mandatory Custom Fields Issue
Hello everyone, we have an issue in Project Server 2019, we created custom fields as mandatory and added it to a PDP. If we try to edit the project information from PDP, it saves the project without validate or fire an error that one of the mandatory fields is empty. if we saved through Micrsoft Project if fires an error normally, also the same case if the user tries to submit workflow stating that mandatory fields is empty. Thanks & Regards Ahmed Amin68Views0likes1Comment
Events
Recent Blogs
- Project 2016 and Project 2019 will reach end of support on October 14, 2025.Oct 14, 202412KViews4likes9Comments
- One of my favourite features in Project Online, and Project Server, has been the portfolio features that allow you do match your plan portfolio against your business drivers to ensure you are gaining...Sep 25, 20243KViews4likes8Comments