2 TopicsWorkload by week/ month export to Excel
I like to use Visual report, but that doesn’t work.. I have MSProject 2016 and office 365. so I have tried to use save as (export) as xls. But I can’t get the load or week or month. anyone that can help out setup in table format. I think… the I can build the rest in Excel if needed br runeSolved128Views0likes4CommentsExporting Project - Resource Usage table with phased time data to excel
Hi Experts, Is there a way to export tasks to excel while retaining the phased time cost data? In an ideal world I would like to export this info and for it to look like this in excel: Export wizard is not doing the trick. Good old copy paste is copying the Resource list, but not the time phase. Any ideas?2.3KViews0likes7Comments