Forum Discussion

PrzywaraL's avatar
PrzywaraL
Copper Contributor
Nov 07, 2023
Solved

Tasks are not visible while trying to link to risks MS Project

I created a project with different tasks, as you can see in the SS.

After that I created a risk. You can see the risk in the second SS. When I tried to link the risk to a task, no task where found. 

I just tried the MS guide: https://support.microsoft.com/de-de/office/hinzuf%C3%BCgen-eines-risikos-zu-einem-projekt-in-project-online-7aa1acc9-50cf-4f15-ac3b-fedf41b31c83

 

I hope someone could help me thanks

 

  • Hello PrzywaraL ,

    Since making the sync tasks to Project site feature active, have you republished the projects? They will not appear in the Task lists on the Project Sites until the project/s have been published again.

    Paul

8 Replies

  • Hello PrzywaraL ,

    Do you sync the tasks to the Project Site? It is this setting on the Enterprise Project Type/s in PWA Settings:

     

    Paul

  • TonyProctor's avatar
    TonyProctor
    Brass Contributor
    Did you publish your schedule and verify the sharepoint site is connected in PWA? Also, I highly recommend Dale Howard MVP's video on how to do the Risk Management in your schedule to see true impacts within your schedule then you can use your SharePoint/Project Sites for the high level rollup of the Issues and Risks. Here's link https://www.youtube.com/watch?v=CpwOJIoYzQg&t=6s
    • PrzywaraL's avatar
      PrzywaraL
      Copper Contributor

      TonyProctor 

      Thank you for your answer,

      i already published my schedule and its also connected. I can see it in my Project Center

      Thank you, The inactive Task feature, is a good help, but can I also connected it then to the risks?

       

      Paul_Mather 

      The sync was not active, I activated it, but it still doesnt work

      • PrzywaraL --

        To answer your question, I believe that a task must be Active so that it can be connected to a Risk. Hope this helps.

Resources