Forum Discussion
PrzywaraL
Nov 07, 2023Copper Contributor
Tasks are not visible while trying to link to risks MS Project
I created a project with different tasks, as you can see in the SS. After that I created a risk. You can see the risk in the second SS. When I tried to link the risk to a task, no task where found. ...
- Nov 13, 2023
Hello PrzywaraL ,
Since making the sync tasks to Project site feature active, have you republished the projects? They will not appear in the Task lists on the Project Sites until the project/s have been published again.
Paul
Paul_Mather
Nov 12, 2023MVP
Hello PrzywaraL ,
Do you sync the tasks to the Project Site? It is this setting on the Enterprise Project Type/s in PWA Settings:
Paul